401 N Ervay St
Dallas, TX 75201
Office spec-suite buildout and mechanical upgrades
A finish-out of existing spec suites for office use was permitted at 401 N Ervay St on February 24, 2026. Additional permits through May 5 cover plumbing, an electrical remodel, and mechanical work including new ductwork and grilles.
Summarized from City of Dallas records · updated May 5, 2026
- Projects
- 4
- 4 filings
- Latest filing
- May 5, 2026
- since Feb 24, 2026
- Largest scope
- —
- Listed value
- —
Permit & project history
4 projects1. demolition existing ductwork not shown to stay on mechanical plans.2. install filter media.3. install new ductwork as shown.4. insulation for new ductwork.5. 50 supply grilles.6. 50 return grilles.7. 10 sidewall supply grilles.8. 72 supply slots.9. 1 sidewall return grille.10. 11 metal cooling only single duct vavs11 16 metal industries fpbs
1. demolition existing ductwork not shown to stay on mechanical plans.2. install filter media.3. install new ductwork as shown.4. insulation for new ductwork.5. 50 supply grilles.6. 50 return grilles.7. 10 sidewall supply grilles.8. 72 supply slots.9. 1 sidewall return grille.10. 11 metal cooling only single duct vavs11 16 metal industries fpbs
City of Dallas permitCommercial Mechanical Permit
Sources: City of Dallas
Questions about 401 N Ervay St
What is being built at 401 N Ervay St?
City of Dallas permits indicate a finish-out of existing spec suites for office use, along with plumbing, electrical, and mechanical work. The finish-out permit, COM-ALT-ADD-26-000332, was filed February 24, 2026.
When were the office suite permits filed at 401 N Ervay?
The office finish-out permit was filed February 24, 2026. Related plumbing, electrical, and mechanical permits were filed March 20, April 13, and May 5, 2026.
What work is planned for the office suites at 401 N Ervay?
The permits describe a finish-out of existing spec suites, plumbing installation with three sinks, an electrical remodel, and mechanical work that includes new ductwork and grilles.
Is a new office building being built at 401 N Ervay St?
The records describe a finish-out of existing spec suites for office use, not construction of a new building.
What's being renovated near Mier Law on Pacific Avenue?
At 401 N Ervay St, about 115 meters from Mier Law at 1700 Pacific Avenue, permits indicate an office spec-suite finish-out and related plumbing, electrical, and mechanical work.
Also being built nearby
All of 75201- 401 North Ervay 22nd · 3pz Property Company LLCFeb 11, 202622nd floor spec suites — renovation/alteration — tenant improvement
- 350 N Ervay StNov 23, 2020Install boiler · 57 m away
- 1600 Pacific AveOct 27, 2020Tc-2020-23039 · 104 m away
- 400 N. Saint Paul Street · Hartford Living, LLCJun 9, 2025The hartford — renovation/alteration — historic renovation of a 15 story masonry office building into a multi-family development with 217 residential apartments on floors 2-13. the 14th floor will be transformed into the residential amenity space · 111 m away
- 400 N St Paul StNov 6, 2025Gas leak atmos locked the meter out we have made the repairs on the gas line and there is no more leaks · 111 m away
- 1700 Pacific Ave · Olymbec Usa, LLCApr 7, 2026Electrical remodel · 115 m away
- 1700 Pacific Avenue · Olymbec Usa, LLCMar 24, 2026Mier law — renovation/alteration — tenant finish out, remodel · 115 m away
- 1909 Bryan StOct 27, 2025Repair of electrical in a dumpster room · 121 m away
- 374 N St Paul StSep 23, 2020Permanent electrical service · 126 m away
- 1919 Bryan StSep 10, 2026Like for like replacement of two split hvac systems. no alterations or changes required · 132 m away
- 350 N St Paul StMar 5, 2026Rpz replacement · 148 m away
- 350 N. Saint Paul St · Bryan Street Office, LPJun 3, 2024Hks renovation - level 01 — renovation/alteration — minor renovations to an existing tenant space · 148 m away