Dallas Fire Station 18 planned for 1205 Patterson Street
A new 24,630-square-foot, two-story Fire Station 18 is planned at 1205 Patterson Street, with four drive-through bays, a mezzanine, storm shelter, air shop and dormitories. The project was registered with TDLR on March 3, 2026; its listed status is Review Complete, and the applicant estimates the project cost at $19 million.
Summarized from Texas Department of Licensing and Regulation records · updated Mar 3, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Mar 3, 2026
- since Mar 3, 2026
- Largest scope
- 24,630 sf
- Estimated cost
- $19M
- state registration
Where this project stands
Approved · construction starts Dec 31, 2026Fire Station 18
24,630 sq ft · $19M est.
- RegisteredMar 3, 2026
- Plan review
- ConstructionDec '26 – Dec '28
- Inspected
- Closed
A 24-month build is scheduled. Bids for subcontractors and suppliers usually close before the start date.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectNew 24,000 sq ft fire station. 2-story, 4 drive-thru bay, fire station with mezzanine, storm shelter, air shop, and dormitories. — fire station 18
TDLR project registrationNew ConstructionReview Complete24,630 sq ft$19M est.- Project #
- TABS2026013948
- Tenant / owner
- Fire Station 18
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 1205 Patterson Street
What is being built at 1205 Patterson Street?
A new Fire Station 18 is planned for the site. The TDLR registration describes a two-story, 24,630-square-foot station with four drive-through bays, a mezzanine, storm shelter, air shop and dormitories.
When was the Fire Station 18 project filed?
The TDLR project registration, TABS2026013948, was filed on March 3, 2026. Its listed status is Review Complete.
How large will the new fire station be?
The TDLR registration lists the project at 24,630 square feet. Its description calls it a new 24,000-square-foot fire station.
How much will Fire Station 18 cost?
The applicant's estimated cost in the TDLR registration is $19 million. This is an estimate for the project, not a confirmed final cost.
What is being built near Burke Bogdanowicz Expansion on Elm Street?
A new Fire Station 18 is planned at 1205 Patterson Street, about 157 meters from the Burke Bogdanowicz Expansion at 1201 Elm Street. The station project was registered with TDLR on March 3, 2026.
Is a new fire station planned near Zero Latency on Ross Avenue?
Yes. Fire Station 18 is planned at 1205 Patterson Street, about 208 meters from Zero Latency at 1001 Ross Avenue. The TDLR registration describes a two-story station with four drive-through bays.
Also being built nearby
All of 75202- 1205 Patterson StOct 27, 2026Site utilities to with in 5' of building
- 1205 Patterson StOct 1, 2026An 8 feet tall construction fence and gates are needed around the property for the construction of fire station #18. the rear yard is on san jacinto. the front yard is on patterson ave. the lot is currently used only for parking
- 1215 Patterson St · Spanky Branch LLCMay 17, 2024Bofa patterson drive-up atm — new construction — install new free-standing atm with drive-up · 9 m away
- 1217 Patterson StSep 14, 2026A temporary construction trailer is going to be located on this site for our use in constructing the fire station #18 on 1205 patterson. the owner of the fire station also owns the 4 lots on the corner which will be our trailer and material storage location. we already have the permit in hand and have also submitted for fence permit for the 5 total lots · 11 m away
- 1217 Patterson StSep 30, 2026An 8 feet tall construction fence and gate are needed around the property for a construction office trailer and for a material laydown area. one side of the lot is on the corner of patterson and n field st.. the other side of the lot faces san jacinto street. the lot is currently used only for parking · 11 m away
- 501 N Field StNov 12, 2026Temporary pole service for construction trailer · 87 m away
- 500 N Griffin StNov 17, 2026Demolish building and slab. no trees · 103 m away
- 1320 San Jacinto StSep 30, 2026An 8 feet tall construction fence and gate are needed around the property for material laydown and parking area. fence will be only on one side of this lot on san jacinto st. the other three sides will not have fencing. they are open to the other enclosed fence areas seeking permit as well. the lot is currently used only for parking. below, in part 2, i provided the full perimeter length of the lot, it is not the same as the fence lf needed for this lot. if that is what is asked, then that is approx. 50 feet long · 107 m away
- 1338 San Jacinto StSep 30, 2026An 8 feet tall construction fence is needed around the property for material laydown and parking area. fence will be needed on san jacinto street and n field street. the other two sides will not have fencing. they are open to the other enclosed fence areas. the lot is currently used only for parking · 117 m away
- 1365 San Jacinto StDec 17, 2020Permanent electrical service · 139 m away
- 1200 Ross AveJan 4, 2021Supergraphics change copy · 152 m away
- 1201 Elm StNov 11, 2020Installation of electric strikes and electric locksets · 157 m away