A commercial alteration permit filed July 2, 2025, describes a first-time coffee shop finish-out with a full-size kitchen at 2350 N Beckley Ave. City of Dallas permits also show electrical and plumbing work in July 2025, new split-system equipment in January 2026, and a vent hood installation in June 2026. The records do not identify a business name or an opening date.
Summarized from City of Dallas, Texas Department of Licensing and Regulation records · updated Jun 24, 2026
- Projects
- 9
- 9 filings
- Latest filing
- Jun 24, 2026
- since Feb 10, 2025
- Largest scope
- 4,274 sf
- Estimated cost
- $400K
- state registration
Permit & project history
9 projects2740 sq ft ground floor, 1534 sq ft mezzanine, 4274 sq ft total addition — modera trinity
TDLR project registrationAdditions to Existing BuildingReview Complete4,274 sq ft$400K est.- Project #
- TABS2025011564
- Tenant / owner
- Inclusion Modera
- Design firm
- Pro
- Contact
- Pro
Sources: City of Dallas · Texas Department of Licensing and Regulation
Questions about 2350 N Beckley Ave
What is being built at 2350 N Beckley Ave in Dallas?
A City of Dallas alteration permit describes a first-time coffee shop finish-out with a full-size kitchen. It was filed July 2, 2025, under permit COM-ALT-ADD-25-000160.
Is a coffee shop opening at 2350 N Beckley Ave?
The permit describes a coffee shop finish-out, but the records do not name a business or provide an opening date.
What permits have been filed for 2350 N Beckley Ave?
The eight City of Dallas permits include alteration, electrical, plumbing, and mechanical work. Recent filings include plumbing on February 5, 2026, and a vent hood installation on June 24, 2026.
Is there a kitchen planned at 2350 N Beckley Ave?
Yes. The July 2, 2025, alteration permit describes a coffee shop finish-out with a full-size kitchen. A July 30, 2025, plumbing permit also mentions a sewer line and grease trap.
What HVAC work is happening at 2350 N Beckley Ave?
Two mechanical permits filed January 7 and 8, 2026, describe two 10-ton split systems with air handlers and condensers. A later permit filed June 24, 2026, covers installation of a vent hood.
What's being built near Birch Construction on N Beckley Ave?
At 2350 N Beckley Ave, about 170 meters from Birch Construction at 131 Yorktown Street, permits describe a coffee shop finish-out with a full-size kitchen. The alteration permit was filed July 2, 2025.
Also being built nearby
All of 75208- 2343 N Beckley AveJul 1, 2025Replaced 2" rpz · 18 m away
- 2320 N Beckley AveOct 5, 2026Replace rtu · 49 m away
- 2324 Beatrice StJul 30, 2026New service for parking lot · 118 m away
- 2318 Beatrice StAug 7, 2025No work electrical release permit · 122 m away
- 2331 Beatrice StNov 24, 2020Service release no work · 128 m away
- 2321 Beatrice StOct 23, 2020Interior / exterior remodel - creating suites 100 and 110, new 2h · 133 m away
- 2313 Beatrice StNov 23, 2020Install fence · 138 m away
- 131 Yorktown Street · Bs Worldwide, LLCJun 16, 2026Birch construction — renovation/alteration — minor tenant improvement of existing space including new offices, open work areas, conference rooms, exercise area with unisex restroom/shower. no contracted work within existing restrooms and mezzanine area. 13,000 sq ft · 170 m away
- 131 Yorktown · Bs Worldwide LLCAug 8, 2024Azzurro living — renovation/alteration — update a/c, update electrical wiring, update restrooms, add a restroom and update existing restroom, paint and install new windows. square footage - 15,086 sq ft · 170 m away
- 131 Yorktown StNov 16, 2026Bu zo birch construction is an existing 1-story building with a mezzanine that is undergoing interior renovation only. areas include offices, conference rooms, training room, huddle rooms, and excercise room. existing mezzanine is existing to remain · 170 m away
- 2330 Langford StJan 19, 2021Build demising wall to create 2 separate suites 100 and 110 plus · 206 m away
- 2317 Langford StMar 24, 2026No work performed. only gas test · 217 m away