groundranger
Active · latest filing Oct 2026Commercial

4800 Langdon Rd

Dallas, TX 75241 · Nia Dal2 - Water Process Expansion, Nia Dal 2 - Gallon Line Expansion + 1 more

Permits show upgrades at an existing water bottling and warehouse facility

Permits indicate exterior upgrades at the existing water bottling and warehouse facility at 4800 Langdon Rd, including a wastewater buffer tank and a new discharge line. A commercial alteration permit for this work was filed October 19, 2026 (COM-ALT-ADD-26-002202); a sanitary-line permit followed on October 27 (COM-PLM-26-004130). Other filings cover truck check-in and check-out stations and warehouse pallet racks.

Summarized from City of Dallas, Texas Department of Licensing and Regulation records · updated Oct 27, 2026

Projects
24
24 filings
Latest filing
Oct 27, 2026
since Nov 5, 2020
Largest scope
13,000 sf
Estimated cost
$2.9M
state registration

Permit & project history

24 projects
  1. Install sanitary line to tank

    Install sanitary line to tank

    City of Dallas permitCommercial Plumbing Permit
    Record
    COM-PLM-26-004130
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Zo bc this project is an "rennovation" to an existing water bottling and warehouse facility. it consists of exterior modifications in support of a new waste water buffer tank and connection to existing process water sanitary line. the modifications include new structural foundations for the tank, associated site improvements (bollards, etc), and a new discharge line. the discharge line will connect to the existing process water sanitary main below grade. there is no new process waste water load; the new tank simply buffers existing approved discharge to achieve a slower rate of discharge. there are no modifications proposed to the existing building or its mechanical systems. all work occurs within 60' of the building and more than 60' from the property line, and entirely within the existing equipment and truck circulation paved area

    Zo bc this project is an "rennovation" to an existing water bottling and warehouse facility. it consists of exterior modifications in support of a new waste water buffer tank and connection to existing process water sanitary line. the modifications include new structural foundations for the tank, associated site improvements (bollards, etc), and a new discharge line. the discharge line will connect to the existing process water sanitary main below grade. there is no new process waste water load; the new tank simply buffers existing approved discharge to achieve a slower rate of discharge. there are no modifications proposed to the existing building or its mechanical systems. all work occurs within 60' of the building and more than 60' from the property line, and entirely within the existing equipment and truck circulation paved area

    City of Dallas permitCommercial Alteration Addition Permit
    Record
    COM-ALT-ADD-26-002202
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. This project is a "rennovation" to an existing water bottling and warehouse facility. it consists of exterior modifications in support of a new waste water buffer tank and connection to existing process water sanitary line. the modifications include new structural foundations for the tank, associated site improvements (bollards, etc), and a new discharge line. the discharge line will connect to the existing process water sanitary main below grade. there is no new process waste water load; the new tank simply buffers existing approved discharge to achieve a slower rate of discharge. there are no modifications proposed to the existing building or its mechanical systems. all work occurs within 60' of the building and more than 60' from the property line, and entirely within the existing equipment and truck circulation paved area

    This project is a "rennovation" to an existing water bottling and warehouse facility. it consists of exterior modifications in support of a new waste water buffer tank and connection to existing process water sanitary line. the modifications include new structural foundations for the tank, associated site improvements (bollards, etc), and a new discharge line. the discharge line will connect to the existing process water sanitary main below grade. there is no new process waste water load; the new tank simply buffers existing approved discharge to achieve a slower rate of discharge. there are no modifications proposed to the existing building or its mechanical systems. all work occurs within 60' of the building and more than 60' from the property line, and entirely within the existing equipment and truck circulation paved area

    City of Dallas permitCommercial Alteration Addition Permit
    Record
    COM-ALT-ADD-26-001887
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Adding power for gates

    Adding power for gates

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-26-003588
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  5. Adding power for automated gates on each side of warehouse in the parking lot

    Adding power for automated gates on each side of warehouse in the parking lot

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-26-003388
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  6. Remove existing membrane and replace with new membrane system

    Remove existing membrane and replace with new membrane system

    City of Dallas permitCommercial Roofing Permit
    Record
    COM-ROOF-26-000121
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  7. 8' tall black vinyl chain link fence

    8' tall black vinyl chain link fence

    City of Dallas permitCommercial Accessory Structure Permit
    Record
    COM-ACC-26-000013
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  8. Bc zo el this project consists of only exterior work. the exterior paving demolition and work is covered under a separate permit. the work in this scope is changing the check-in and check-out stations for arriving and departing trucks. conduit is proposed to run from the existing building to each of these check-out and check-in areas to power the required equipment.there is no proposed change to the building size, occupancy, use, or classification

    Bc zo el this project consists of only exterior work. the exterior paving demolition and work is covered under a separate permit. the work in this scope is changing the check-in and check-out stations for arriving and departing trucks. conduit is proposed to run from the existing building to each of these check-out and check-in areas to power the required equipment.there is no proposed change to the building size, occupancy, use, or classification

    City of Dallas permitCommercial Alteration Addition Permit
    Record
    COM-ALT-ADD-26-001175
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  9. Mcr permitting & installing 108 bays of pallet racks. there will be no alteration to building footprint/shell. no additional square footage is being added and area is not open to public. all alteration areas are designated on the key plan. racking to be installed by wize solutions, inc

    Mcr permitting & installing 108 bays of pallet racks. there will be no alteration to building footprint/shell. no additional square footage is being added and area is not open to public. all alteration areas are designated on the key plan. racking to be installed by wize solutions, inc

    City of Dallas permitCommercial Alteration Addition Permit
    Record
    COM-ALT-ADD-26-000407
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  10. Remove 1" rpz sn a78312- device no longer needed remove 4" rpz sn yj0336 remove 6" dc sn ze-1231 install 6" rpz sn yn-1071 to replace 6" dc above**this work is unrelated to any other backflow assembly work at this location

    Remove 1" rpz sn a78312- device no longer needed remove 4" rpz sn yj0336 remove 6" dc sn ze-1231 install 6" rpz sn yn-1071 to replace 6" dc above**this work is unrelated to any other backflow assembly work at this location

    City of Dallas permitCommercial Plumbing Permit
    Record
    COM-PLM-26-001344
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  11. Remove 1" rpz sn a78312- device no longer neededremove 4" rpz sn yj0336remove 6" dc sn ze-1231install 6" rpz sn yn-1071 to replace 6" dc above

    Remove 1" rpz sn a78312- device no longer neededremove 4" rpz sn yj0336remove 6" dc sn ze-1231install 6" rpz sn yn-1071 to replace 6" dc above

    City of Dallas permitCommercial Plumbing Permit
    Record
    COM-PLM-26-001259
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  12. Install 3 backflow devices

    Install 3 backflow devices

    City of Dallas permitCommercial Plumbing Permit
    Record
    COM-PLM-26-000874
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  13. This scope consists of modifications to an existing building's joist, girder, and overhead structural system to provide additional support to joist-mounted cable tray, process piping, and mechanical rooftop unit supports. no square footage is being added to the facility

    This scope consists of modifications to an existing building's joist, girder, and overhead structural system to provide additional support to joist-mounted cable tray, process piping, and mechanical rooftop unit supports. no square footage is being added to the facility

    City of Dallas permitCommercial Alteration Addition Permit
    Record
    COM-ALT-ADD-25-000660
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  14. Niagara bottling, llc (owner) is expanding their existing facility in dallas, tx. theproject includes installing production, packaging, and support equipment infrastructureto accommodate immediate and future production requirements. the existing facilitywill self-manufacture plastic containers, then fill and package bottles for distribution.-temp power for construction trailer- power to be sourced from existing panel boards-temp construction 7-50amp spider boxes sourced from existing panel boards 208v-installation of ceiling support cable tray system, for power and control cable routing -installation of 480v branch circuits from msb to process/utility equipment as detailed in plans-installation of all 480v branch circuits from pdp/ lps for process/utility equipment as detailed in plans-installation of all 120v branch circuits from ipp to process/utility equipment as detailed in plans-installation of all pump feeds from associated mcc sections-setting and anchors all pdp,ipp,mcc power distribution equipment-installation of all control wiring for process/utility equipment per process engineer design control out of several ecp/plc's- full installation of raceway systems, and cabling for oem manufacturing equipment oem-krones. as per detailed in plans-full installation of raceway systems, and cabling for oem manufacturing equipment oem-lantech stretch wrapper. as per detailed in plans

    Niagara bottling, llc (owner) is expanding their existing facility in dallas, tx. theproject includes installing production, packaging, and support equipment infrastructureto accommodate immediate and future production requirements. the existing facilitywill self-manufacture plastic containers, then fill and package bottles for distribution.-temp power for construction trailer- power to be sourced from existing panel boards-temp construction 7-50amp spider boxes sourced from existing panel boards 208v-installation of ceiling support cable tray system, for power and control cable routing -installation of 480v branch circuits from msb to process/utility equipment as detailed in plans-installation of all 480v branch circuits from pdp/ lps for process/utility equipment as detailed in plans-installation of all 120v branch circuits from ipp to process/utility equipment as detailed in plans-installation of all pump feeds from associated mcc sections-setting and anchors all pdp,ipp,mcc power distribution equipment-installation of all control wiring for process/utility equipment per process engineer design control out of several ecp/plc's- full installation of raceway systems, and cabling for oem manufacturing equipment oem-krones. as per detailed in plans-full installation of raceway systems, and cabling for oem manufacturing equipment oem-lantech stretch wrapper. as per detailed in plans

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-25-002557
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  15. Relocate supply fans sf7 and sf8 with associated supportsremove and haul off exhausts and duct work servicing air cooled compressorfurnish and install (7) packaged roof top units with associated ductwork and supportsfurnish and install (2) make up air units with associated ductwork and supportsfurnish and install (10) roof exhaust fans with associated ductwork and supportsfurnish and install (6) roof hoods with assocaited ductwork and supportsfurnish and install (10) supply fans with associated ductwork and supportsfurnish and install (4) fire dampers with associated access doors, fire stopping, ductwork and supportsfurnish and install (5) louvers with associated ductwork and supportsfurnish and install (22) air devices with associated ductwork and supportsfurnish and install (1) motorized damper with associated ductwork and supportsfurnish and install (13) drum louver boxes with associated ductwork and supports

    Relocate supply fans sf7 and sf8 with associated supportsremove and haul off exhausts and duct work servicing air cooled compressorfurnish and install (7) packaged roof top units with associated ductwork and supportsfurnish and install (2) make up air units with associated ductwork and supportsfurnish and install (10) roof exhaust fans with associated ductwork and supportsfurnish and install (6) roof hoods with assocaited ductwork and supportsfurnish and install (10) supply fans with associated ductwork and supportsfurnish and install (4) fire dampers with associated access doors, fire stopping, ductwork and supportsfurnish and install (5) louvers with associated ductwork and supportsfurnish and install (22) air devices with associated ductwork and supportsfurnish and install (1) motorized damper with associated ductwork and supportsfurnish and install (13) drum louver boxes with associated ductwork and supports

    City of Dallas permitCommercial Mechanical Permit
    Record
    COM-MEC-25-000901
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  16. Furnish and isntall the following equipment/fixtures with associated plumbing(1) electric water cooler(3) floor sinks(26) floor clean outs(1) sink(4) emergency eyewash/shower stations(15) fd1's(7) hd1's(1) hd3(1) hd8a(2) hd8b's(2) td0a's(3) td0b's(1) td1(1) td2(1) td3a(1) td3b(1) td4a(1) td4b(1)td5(3) td6's(1) td7(1) wh1

    Furnish and isntall the following equipment/fixtures with associated plumbing(1) electric water cooler(3) floor sinks(26) floor clean outs(1) sink(4) emergency eyewash/shower stations(15) fd1's(7) hd1's(1) hd3(1) hd8a(2) hd8b's(2) td0a's(3) td0b's(1) td1(1) td2(1) td3a(1) td3b(1) td4a(1) td4b(1)td5(3) td6's(1) td7(1) wh1

    City of Dallas permitCommercial Plumbing Permit
    Record
    COM-PLM-25-002028
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  17. Installation of underground primary service conduits & util-xmfr padsinstallation of underground secondary conduits from util-xfmr into new 400amp msbsinstallation of underground conduits from msb to process equipment- conduit onlyinstallation of roof top units- raceways & conductorslighting package per plansconvi. receptacles for new utility rm & wp rmpower for cooler mau & evapspower for cooler room with build in heat trace

    Installation of underground primary service conduits & util-xmfr padsinstallation of underground secondary conduits from util-xfmr into new 400amp msbsinstallation of underground conduits from msb to process equipment- conduit onlyinstallation of roof top units- raceways & conductorslighting package per plansconvi. receptacles for new utility rm & wp rmpower for cooler mau & evapspower for cooler room with build in heat trace

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-25-002494
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  18. Mcr the da2-5 csd project involves adding a new carbonated soft drink (csd) production line to an existing beverage bottling facility in dallas, texas. the scope consists of: interior: limited removal of mechanical, plumbing, and electrical elements for new or relocated systems. new moderate-hazard factory industrial group f-1 areas including; batching, cip (clean-in-place), utility, and a boiler room. new high-hazard group h-3 including; recycler area, cooler, and freezer. new interior thickened, reinforced slabs to support new equipment installation of additional drains to accommodate the expanded processing area. new mechanical, plumbing, and electrical systems in support of the above modifications. modifications to the existing sprinkler and alarm systems as necessary to accommodate above modifications (deferred submittal). exterior: exterior upgrades include the addition of a cooling tower, two new transformers, one new resin silo installed on an existing topping pedestal, one new water silo, a co2 and nitrogen tank, and a wet well. a new entrance ramp and overhead door will be added. new process waste lift station general: the project is located at 4800 langdon road, dallas, tx 75241. the total area of scope is approximately 70,000 sq ft the scope will be made up of architectural and engineering documents relative to the work. no additional building height or area is being added

    Mcr the da2-5 csd project involves adding a new carbonated soft drink (csd) production line to an existing beverage bottling facility in dallas, texas. the scope consists of: interior: limited removal of mechanical, plumbing, and electrical elements for new or relocated systems. new moderate-hazard factory industrial group f-1 areas including; batching, cip (clean-in-place), utility, and a boiler room. new high-hazard group h-3 including; recycler area, cooler, and freezer. new interior thickened, reinforced slabs to support new equipment installation of additional drains to accommodate the expanded processing area. new mechanical, plumbing, and electrical systems in support of the above modifications. modifications to the existing sprinkler and alarm systems as necessary to accommodate above modifications (deferred submittal). exterior: exterior upgrades include the addition of a cooling tower, two new transformers, one new resin silo installed on an existing topping pedestal, one new water silo, a co2 and nitrogen tank, and a wet well. a new entrance ramp and overhead door will be added. new process waste lift station general: the project is located at 4800 langdon road, dallas, tx 75241. the total area of scope is approximately 70,000 sq ft the scope will be made up of architectural and engineering documents relative to the work. no additional building height or area is being added

    City of Dallas permitCommercial Alteration Addition Permit
    Record
    COM-ALT-ADD-25-000883
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  19. Installation of water purification equipment inside an extension to niagara bottling existing lease space. — niagara dallas

    TDLR project registrationRenovation/AlterationReview Complete2,100 sq ft$515K est.
    Tenant / owner
    Nia Dal2 - Water Process Expansion
    Design firm
    Pro
    Contact
    Pro
  20. Addition of a distilled water gallon line to an existing niagara water bottling company. outdoor equipment and a new check-in check-out kiosk are part of this scope. — niagara dallas

    TDLR project registrationRenovation/AlterationReview Complete13,000 sq ft$2.9M est.
    Tenant / owner
    Nia Dal 2 - Gallon Line Expansion
    Design firm
    Pro
    Contact
    Pro
  21. Installation of an air-cooled chiller at the exterior of the building. thickened slab for air-cooled chiller. existing building joist reinforcement to host new pipe routing. — niagara dallas 2

    TDLR project registrationAdditions to Existing BuildingReview Complete550 sq ft$218K est.
    Tenant / owner
    Nia Dal 2 - Chilled Water Expansion
    Design firm
    Pro
    Contact
    Pro
  22. Interior remodel only

    Interior remodel only

    City of Dallas permitBuilding (BU) Commercial Renovation$282K
    Record
    2101081041
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  23. Interior remodel only

    Interior remodel only

    City of Dallas permitBuilding (BU) Commercial Renovation$260K
    Record
    2011301145
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  24. Installation of access control system

    Installation of access control system

    City of Dallas permitSecurity System (SE) Commercial Alteration$38K
    Record
    2009301005
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Dallas · Texas Department of Licensing and Regulation

Questions about 4800 Langdon Rd

What is being built at 4800 Langdon Rd in Dallas?

Permits indicate upgrades to an existing water bottling and warehouse facility, including a wastewater buffer tank, supporting foundations and a discharge line. The filings do not describe a new building.

Is the project at 4800 Langdon Rd a new warehouse?

The permits describe work at an existing facility, with no change to the building’s size or footprint in the filings about truck stations and pallet racks. The wastewater tank work is also described as exterior modifications to the existing site.

What is the wastewater tank work at 4800 Langdon Rd?

A commercial alteration permit filed October 19, 2026 (COM-ALT-ADD-26-002202), describes a buffer tank and discharge line connected to the existing process-water sanitary line. The permit says the tank is intended to slow the rate of an already approved discharge.

Are truck check-in stations being changed at 4800 Langdon Rd?

Yes. A commercial alteration permit filed June 16, 2026 (COM-ALT-ADD-26-001175), covers changes to the truck check-in and check-out stations and conduit to power equipment.

Are pallet racks being installed at 4800 Langdon Rd?

A commercial alteration permit filed April 28, 2026 (COM-ALT-ADD-26-000407), covers installation of 108 bays of pallet racks. The filing says the work adds no square footage and does not change the building footprint.

When were permits filed for work at 4800 Langdon Rd?

The records provided span October 1, 2025, through October 27, 2026. Recent filings include the wastewater tank alteration permit on October 19, 2026, and a sanitary-line permit on October 27, 2026.

Also being built nearby

All of 75241

More demolitions in 75241, warehouses & industrial in 75241, new homes in 75241.

Get alerts for 4800 Langdon Rd