HVAC and water-heater replacements at 8404 Forest Ln
City of Dallas permits filed from June 2025 through August 2026 document HVAC system replacements and a water-heater swap at 8404 Forest Ln. The records describe equipment work, not construction of a new building.
Summarized from City of Dallas records · updated Aug 17, 2026
- Projects
- 9
- 9 filings
- Latest filing
- Aug 17, 2026
- since Jun 2, 2025
- Largest scope
- —
- Listed value
- —
Permit & project history
9 projectsReplace hvac system with goodman 2 ton performance straight cool upflow barge condo unit full system; no duct work
Replace hvac system with goodman 2 ton performance straight cool upflow barge condo unit full system; no duct work
City of Dallas permitResidential Mechanical Permit
Sources: City of Dallas
Questions about 8404 Forest Ln
What is being built at 8404 Forest Ln?
The Dallas permits describe HVAC system replacements and a water-heater swap, not a new building. The latest listed permit, RES-MEC-26-004473, was filed August 17, 2026, for an HVAC replacement.
Is a new apartment building going up at 8404 Forest Ln?
The listed permits document mechanical and plumbing work, including HVAC replacements and a water-heater swap. They do not describe construction of a new apartment building.
When were permits filed for work at 8404 Forest Ln?
The earliest listed filing was June 2, 2025, and the latest was August 17, 2026. The records cover HVAC and water-heater work.
What does permit RES-MEC-26-004473 cover?
Filed August 17, 2026, the City of Dallas permit describes replacing an HVAC system with a Goodman 2-ton straight-cool upflow system. It specifies no duct work.
Was a water heater permitted at 8404 Forest Ln?
Yes. Permit RES-PLM-25-000908, filed June 2, 2025, covers swapping out a 38-gallon electric water heater on the bottom floor near the laundry room.
How many HVAC permits are listed for 8404 Forest Ln?
Four of the five listed permits cover HVAC work. They include filings dated September 26, 2025, May 7, 2026, July 20, 2026, and August 17, 2026.
Also being built nearby
All of 75243- 8443 Stults RdAug 4, 2025Gas test · 153 m away
- 11917 Oberlin DrAug 27, 2026Upgrade electrical service · 266 m away
- 11903 Oberlin DrJan 8, 2021Addition to sfd · 276 m away
- 11850 Oberlin DrMar 2, 2026Gas test · 302 m away
- 8235 Forest LnJul 28, 2026Replacing gas yard service line · 309 m away
- 8231 Forest LnOct 28, 20263 hvac systems ductwork exhaust fans dryer and venthood · 315 m away
- 12008 Oberlin DrOct 8, 2025Relocating the electrical panel · 329 m away
- 12014 Oberlin DrMay 1, 2026Finish project from previous permit 2304123043 · 334 m away
- 12020 Oberlin DrSep 23, 2020Service release no work · 338 m away
- 11843 Oberlin DrAug 27, 2025Gas test is currently off house occupied · 355 m away
- 11939 Hoblitzelle DrAug 24, 2026Install anew 3 ton gas system · 381 m away
- 11932 Hoblitzelle DrAug 5, 2026Gas pressure test · 383 m away