Recent · latest filing Mar 2026Commercial
9670 Forest Ln
Dallas, TX 75243
100-amp main disconnect replacement at 9670 Forest Ln
A commercial electrical permit indicates a 100-amp main disconnect is being replaced at 9670 Forest Ln. The City of Dallas permit was filed March 4, 2026.
Summarized from City of Dallas records · updated Mar 4, 2026
- Projects
- 5
- 5 filings
- Latest filing
- Mar 4, 2026
- since Nov 20, 2020
- Largest scope
- —
- Listed value
- $1
- partial · often understated
Permit & project history
5 projectsSources: City of Dallas
Questions about 9670 Forest Ln
What work is permitted at 9670 Forest Ln in Dallas?
The City of Dallas record describes replacement of a 100-amp main disconnect under commercial electrical permit COM-ELC-26-000953.
When was the electrical permit filed for 9670 Forest Ln?
The permit was filed March 4, 2026.
What is permit COM-ELC-26-000953 for?
It is a commercial electrical permit to replace a 100-amp main disconnect at 9670 Forest Ln.
Is a new building being constructed at 9670 Forest Ln?
The available permit record describes electrical work to replace a main disconnect, not new construction.
How much will the work at 9670 Forest Ln cost?
The permit record does not report a project valuation or cost estimate.
Also being built nearby
All of 75243- 9669 Forest LnFeb 11, 2026Gas leak building. 13 laundry center · 34 m away
- 9690 Forest LnJun 18, 2025Installing 51 steel pilings working on building #66 · 63 m away
- 9708 Forest LnFeb 2, 2026Building 39-unit 3904. meter base repair · 133 m away
- 9600 Forest LnMay 20, 2026We need a permit on the building meter here to restore the power. no work to be done, no unit number. service address is 9600 forest ln hlts 3 esi id is 10443720003314312. no meter is there · 178 m away
- 9659 Forest LnSep 10, 2026Electric permit needed for service release of building j to reactivate, no work required · 184 m away
- 9653 Forest LnJan 2, 2026Need a permit for oncor to re-open the electric account in building j · 197 m away
- 9637 Forest LnOct 27, 2026Locate and repair any leaks located at gas line at property office. pressure test line, request gas release and have repair inspected so property can have gas service restored · 229 m away
- 9590 Forest LnMar 9, 2026Replacing the disconnect and lug · 238 m away
- 9759 Forest Lane · City Of Dallas, Park & Recreation DepartmentAug 1, 2025Forest audelia recreation center — renovation/alteration — convert portion of an existing shopping center site to be used as a city owned urban park. work consists of demolition of parking/paving and fencing with construction of a new landscaped park with playground, splash pad, sidewalks and revised parking · 242 m away
- 9759 Forest LnNov 18, 2026Installation of floor boxes and associated conduit and stub outs in slab · 242 m away
- 9744 Forest LnJul 29, 2025Inspect building 9 house meter. need meter release sent to oncor to reconnect power to house panel · 274 m away
- 9750 Forest LnDec 22, 2025Oncor removed the meter for unit 601 we need it back to get power back on but need it inspected first · 297 m away