Electrical panel and tankless water heater replacements
City of Dallas permits at 9806 Matchpoint Pl cover replacement of an electrical panel and meter base, and replacement of an existing tankless water heater. The electrical permit was filed September 15, 2025 (RES-ELC-25-003071), followed by the plumbing permit on October 20, 2025 (RES-PLM-25-006284). The records describe work at an occupied residence, not a new building.
Summarized from City of Dallas records · updated Oct 20, 2025
- Projects
- 2
- 2 filings
- Latest filing
- Oct 20, 2025
- since Sep 15, 2025
- Largest scope
- —
- Listed value
- —
Permit & project history
2 projectsSources: City of Dallas
Questions about 9806 Matchpoint Pl
What work is permitted at 9806 Matchpoint Pl?
The City of Dallas issued permits for panel and meter base replacement and replacement of an existing electrical tankless water heater.
Is a new home being built at 9806 Matchpoint Pl?
The two records describe electrical and plumbing work at an occupied residence, not new home construction.
When was the electrical work permitted at 9806 Matchpoint Pl?
The electrical permit, RES-ELC-25-003071, was filed September 15, 2025, for panel and meter base replacement.
When was the tankless water heater replacement permitted?
The City of Dallas plumbing permit, RES-PLM-25-006284, was filed October 20, 2025.
Are the permits for a new water heater or an existing one?
The plumbing permit describes installing or replacing an existing electrical tankless water heater with a new one.
How many permits are listed for 9806 Matchpoint Pl?
Two City of Dallas permits are listed: one for electrical work and one for plumbing work.
Also being built nearby
All of 75243- 9810 Matchpoint PlDec 19, 202512’ ft tunnel to fix water leak and flange repair · 2 m away
- 12219 Center Court DrMay 28, 2026Correct height of toilet flance in water closet · 28 m away
- 9843 Baseline DrNov 2, 20269843 baseline install 8 concrete pilings to stabilize foundation · 84 m away
- 9810 Baseline DrOct 20, 2025Replaced 3 ton complete system · 86 m away
- 9838 Baseline DrDec 2, 2025Full rewire per nec · 89 m away
- 12226 Wightman PlJan 7, 2021Foundation repair · 96 m away
- 12222 Wightman PlSep 4, 202540 gal elec lowboy water heater · 98 m away
- 12304 Halima StJun 24, 2026This is part of a board of adjustment case (# boa-255-000106) and diana barkume at the planning department can provide you with the pertinent information. i propose to have installed an 8-ft board-on-board cedar fence on my property line running parallel to chimney hill lane up to my sight triangle. there will also be an 8-ft board-on-board gate perpendicular to this fencing and running up to my house.where the sight triangle starts, i plan on having installed a 6-ft cedar fence that is no more than 50% opaque and continuing that fencing along my property line on ferris creek lane. i need to know if a permit will be required for the whole fence, or just the 8-ft part, because the zoninig is multi-family and my proeprty lien on ferris creek lane is considered front yard. the boa approved my sight triangle line to be along the same line that the existing brick wall is on. the whole brick wall along my property lines will be demolished in favor of building the new wood fence · 110 m away
- 9714 Baseline DrSep 30, 20264-ton heat pump condenser with 88k btus air handler changeout · 112 m away
- 9709 Chimney Hill LnOct 1, 2025Juarez landscaping and construction will be constructing a privacy fence made of cedar wood, which will measure 388 feet in width and stand 8 feet tall, featuring a board-on-board design. the project will begin with the demolition of the existing brick wall, which is also 388 feet long. once that is completed, we will remove and haul away the debris. next, we will start working on the fence by installing 10-foot tall metal posts, which will be dug 2 feet into the ground and secured with concrete. after the concrete has cured, we will install horizontal rails made of pressure-treated pine wood, , and secure them with brackets and screws.once the rails are properly installed, we will add cedar wood boards in a board-on-board style, using 8x5.5 inch boards. finally, we will add a cedar trim and stain the fence on both sides. the new fence will be constructed in the same location as the current brick wall after it has been removed · 115 m away
- 12305 Halima StSep 8, 2026The existing brick wall has partially fallen due to storms occured last year and a month ago. to demolish the remaining wall and replace the whole brick wall with 101 ft board-on-board fence, 8ft pacific cedar prime, 5.5" cedar prime,10 ft 13-gauge metal fence posts. it has been approved by boa. the case number is boa-25-000104 · 116 m away
- 9655 Chimney Hill LnJul 29, 2026Repair meterbase per oncor. building 24, apartment 1004. meter has been removed by oncur. customer is currently without power · 142 m away