7805 Scotia Dr
Dallas, TX 75248
Home HVAC replacements and bathroom plumbing work
Permits at 7805 Scotia Dr indicate residential HVAC replacements and bathroom plumbing work, not a new building. The plumbing permit was filed May 28, 2025, followed by furnace replacement on March 19, 2026, and coil and condenser replacement on June 16, 2026.
Summarized from City of Dallas records · updated Jun 16, 2026
- Projects
- 3
- 3 filings
- Latest filing
- Jun 16, 2026
- since May 28, 2025
- Largest scope
- —
- Listed value
- —
Permit & project history
3 projectsReplace coil & condenser with 2 ton goodman economy 14 seer horizontal (a cabinet) evaporator coil and condenser; no duct work
Replace coil & condenser with 2 ton goodman economy 14 seer horizontal (a cabinet) evaporator coil and condenser; no duct work
City of Dallas permitResidential Mechanical PermitRe route west side middle bath outside around to front and connect to main sewer line by crosswalk
Re route west side middle bath outside around to front and connect to main sewer line by crosswalk
City of Dallas permitResidential Plumbing Permit
Sources: City of Dallas
Questions about 7805 Scotia Dr
What is being built at 7805 Scotia Dr in Dallas?
City of Dallas permits indicate home HVAC replacements and bathroom plumbing work. The records do not describe a new building.
When were permits filed for work at 7805 Scotia Dr?
The plumbing permit was filed May 28, 2025. HVAC permits followed on March 19, 2026, and June 16, 2026.
Is a new house being built at 7805 Scotia Dr?
The records provided list residential mechanical and plumbing permits, not a new-home construction permit.
What HVAC work is permitted at 7805 Scotia Dr?
Permit RES-MEC-26-001188, filed March 19, 2026, covers a furnace replacement. Permit RES-MEC-26-003010, filed June 16, 2026, covers a coil and condenser replacement.
What plumbing work is permitted at 7805 Scotia Dr?
Permit RES-PLM-25-000754, filed May 28, 2025, describes rerouting plumbing from a bathroom on the west side of the home and connecting it to the main sewer line.
Also being built nearby
All of 75248- 7804 Scotia DrJan 20, 2026Full under slab sewer pipe replacement - does notinclude bar sinkexcavation to, re-route / replace (left side frontbathroom, left side back bathroom, right side bathroom, kitchen &washer line under home sewer pipes only) of the plumbing sewerdrain pipe under the home only. our plan reroutesthe under-slab/home sewer pipe and connects it back into the yardsewer line at the city tap area , effectively replacing the yard sewerline as well · 13 m away
- 7806 Scotia DrMar 20, 2026Gas test · 14 m away
- 7819 Scotia DrJul 24, 2026Replace 4 ton gas hvac unit · 39 m away
- 7818 Scotia DrJun 26, 2025Install 5 ton a/c system complete · 41 m away
- 7821 Scotia DrAug 11, 20253 ton split gas system no ductwork · 45 m away
- 7820 Pencross LnSep 12, 2025Mcrbat for the installation of 40 rooftop solar panels and 3 batteries · 85 m away
- 7801 Pencross LnOct 30, 2025Replacing electric panel, whole home surge protector, gfci upgrade · 90 m away
- 7811 Pencross LnJul 13, 2026Sewer/line replacement · 97 m away
- 7819 Pencross LnNov 6, 2026Sewer repipe below slab · 97 m away
- 7815 La Cabeza DrSep 22, 2026Electrical work for patio cover · 106 m away
- 7821 La Cabeza DrNov 3, 202550 gallon ao smith gas water heater installation · 115 m away
- 7826 La Cabeza DrApr 7, 202611 single press concrete piers with rebar reinforcement3 exterior concrete breakout and repatch 2x2 · 136 m away