Terminal E elevator replacement registered at DFW Airport

An existing elevator at Dallas Fort Worth International Airport’s Terminal E is slated for replacement in its current shaft. The project was registered with the Texas Department of Licensing and Regulation on May 29, 2025; the applicant estimated its cost at $500,000.

Summarized from Texas Department of Licensing and Regulation records · updated May 29, 2025

Projects
1
1 filings
Latest filing
May 29, 2025
since May 29, 2025
Largest scope
400 sf
Estimated cost
$500K
state registration

Where this project stands

Finishing up · inspection next

Conveyance Replacement at Terminal E

400 sq ft · $500K est.

  1. RegisteredMay 29, 2025
  2. Plan review
  3. ConstructionAug '25 – Aug '26
  4. Inspectednow
  5. Closed

Scheduled to finish Aug 1, 2026; the state inspection hasn't been filed yet.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Replace existing elevator with new elevator in existing shaft. — dallas fort worth international airport terminal e

    TDLR project registrationRenovation/AlterationReview Complete400 sq ft$500K est.
    Tenant / owner
    Conveyance Replacement At Terminal E
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 2610 N International Parkway

What is being built at 2610 N International Parkway?

The project is replacing an existing elevator at Terminal E with a new elevator in the existing shaft. It was registered on May 29, 2025, under TDLR project number TABS2025020001.

Is Terminal E at DFW getting a new elevator?

A TDLR registration describes replacing an existing elevator with a new one in the same shaft. The registration date is May 29, 2025.

When was the Terminal E elevator replacement registered?

The project was registered with the Texas Department of Licensing and Regulation on May 29, 2025. Its TDLR project number is TABS2025020001.

How much is the Terminal E elevator project estimated to cost?

The applicant estimated the project cost at $500,000 in its TDLR registration. This is an estimate, not a confirmed final cost.

Where will the new elevator be installed at DFW Airport?

The project description says the new elevator will go in the existing shaft at Terminal E. The registration lists 400 square feet for the project.