4275 Strategy Ave, Dfw Airport
Dallas, TX 75621 · Amazon Sfw4 2026 Ssd3.0 Program, Sub Same Day Sfw1
Conveyor and sortation equipment planned inside existing facility
A TDLR registration filed March 24, 2026, describes installing conveyor and sortation equipment inside the existing facility at 4275 Strategy Ave. The work includes supports and electrical controls; the applicant’s estimated project cost is $12,792,257.
Summarized from Texas Department of Licensing and Regulation records · updated Mar 24, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Mar 24, 2026
- since Oct 6, 2025
- Largest scope
- 450,498 sf
- Estimated cost
- $37M
- state registration
Where this project stands
Finishing up · inspection nextAmazon SFW4 2026 SSD3.0 Program
38,025 sq ft · $13M est.
- RegisteredMar 24, 2026
- Plan review
- ConstructionApr '26 – Sep '26
- Inspectednow
- Closed
Scheduled to finish Sep 23, 2026; the state inspection hasn't been filed yet.
4 contacts on this project · 4 phone numbers
Permit & project history
2 projectsInstallation of conveyor and sortation equipment interior to an existing facility. includes the associated supports and electrical controls. — sfw4
TDLR project registrationRenovation/AlterationReview Complete38,025 sq ft$13M est.- Project #
- TABS2026015752
- Tenant / owner
- Amazon Sfw4 2026 Ssd3.0 Program
- Design firm
- Pro
- Contact
- Pro
Interior fit out of distribution warehouse and accessory spaces — sfw1
TDLR project registrationRenovation/AlterationInspection Complete450,498 sq ft$37M est.- Project #
- TABS2026002654
- Tenant / owner
- Sub Same Day Sfw1
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 4275 Strategy Ave, Dfw Airport
What is being built at 4275 Strategy Ave?
A TDLR registration describes installing conveyor and sortation equipment inside an existing facility, with associated supports and electrical controls. The registration was filed March 24, 2026.
Is this a new building at 4275 Strategy Ave?
The registration describes renovation work inside an existing facility, not construction of a new building.
What is the project at 4275 Strategy Ave for?
The registered work is an Amazon SFW4 program involving conveyor and sortation equipment. The record does not specify any other purpose.
How much will the 4275 Strategy Ave project cost?
The applicant’s estimated cost is $12,792,257, according to TDLR registration TABS2026015752. This is an estimate, not a confirmed final cost.
How large is the project at 4275 Strategy Ave?
The TDLR registration lists a project area of 38,025 square feet.
When was the 4275 Strategy Ave project registered?
The TDLR registration, TABS2026015752, was filed March 24, 2026, and its status is listed as Review Complete.