groundranger
Recent · latest filing Jan 2026Commercial

401 Riverbend Way

Dayton, TX 77535 · Omnisource Metal Recycling Facility (dayton), Omnisource - Administration Building 1 + 2 more

OmniSource plans 3,490-square-foot shredder building in Dayton

A 3,490-square-foot metal shredder building and associated site improvements are planned for the OmniSource Metal Recycling Facility at 401 Riverbend Way in Dayton. The project was registered with the Texas Department of Licensing and Regulation on January 12, 2026; its review is marked complete. The applicant-estimated project cost is $10 million.

Summarized from Texas Department of Licensing and Regulation records · updated Jan 12, 2026

Projects
4
4 filings
Latest filing
Jan 12, 2026
since Mar 3, 2025
Largest scope
8,764 sf
Estimated cost
$10M
state registration

Where this project stands

Under construction

Omnisource Metal Recycling Facility (Dayton)

3,490 sq ft · $10M est.

  1. RegisteredJan 12, 2026
  2. Plan review
  3. ConstructionJan '26 – Dec '26
  4. Inspected
  5. Closed
96% through of a 11-month buildJan 12, 2026 → Dec 1, 2026

4 contacts on this project · 2 phone numbers

Permit & project history

4 projects
  1. Ground up construction of 3,490 sq ft metal building and associated site improvements. — shredder building

    TDLR project registrationNew ConstructionReview Complete3,490 sq ft$10M est.
    Tenant / owner
    Omnisource Metal Recycling Facility (dayton)
    Design firm
    Pro
    Contact
    Pro
  2. 8,764 sq ft ground-up construction of pemb administration building with associated site improvements. — omnisource - administration building 1

    TDLR project registrationNew ConstructionReview Complete8,764 sq ft$2.3M est.
    Tenant / owner
    Omnisource - Administration Building 1
    Design firm
    Pro
    Contact
    Pro
  3. 4,500 sq ft ground-up construction of pemb retail building with associated site improvements. — omnisource - retail building 3

    TDLR project registrationNew ConstructionReview Complete4,500 sq ft$881K est.
    Tenant / owner
    Omnisource - Retail Building 3
    Design firm
    Pro
    Contact
    Pro
  4. 5,600 sq ft ground-up construction of pemb maintenance building with associated site improvements. — omnisource - maintenance building 2

    TDLR project registrationNew ConstructionReview Complete5,600 sq ft$1.5M est.
    Tenant / owner
    Omnisource - Maintenance Building 2
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 401 Riverbend Way

What is being built at 401 Riverbend Way in Dayton?

The project registration describes ground-up construction of a 3,490-square-foot metal shredder building and associated site improvements for the OmniSource Metal Recycling Facility.

Is a new shredder building planned for the OmniSource facility in Dayton?

Yes. A TDLR project registration filed January 12, 2026, describes a new 3,490-square-foot metal building identified as a shredder building.

When was the OmniSource Dayton project registered?

The project was registered with the Texas Department of Licensing and Regulation on January 12, 2026. Its review status is listed as complete.

How large is the new building at 401 Riverbend Way?

The registered project describes a 3,490-square-foot metal building, along with associated site improvements.

What is the estimated cost of the OmniSource project in Dayton?

The TDLR registration lists an estimated project cost of $10 million. This is the applicant's estimate for the project.

More retail spaces in 77535.