DFW Hangar 4 slab repairs and renovations

A 28,000-square-foot renovation at Hangar 4 includes installing helical piers to raise a settled slab, renovating a restroom, replacing electrical switchgear and feeders, and site work for trees and drainage. The project was registered with the Texas Department of Licensing and Regulation on November 12, 2025. The applicant estimated the project cost at $6.5 million.

Summarized from Texas Department of Licensing and Regulation records · updated Nov 12, 2025

Projects
1
1 filings
Latest filing
Nov 12, 2025
since Nov 12, 2025
Largest scope
28,000 sf
Estimated cost
$6.5M
state registration

Where this project stands

Under construction

DFW Hangar 4 Slab Repairs

28,000 sq ft · $6.5M est.

  1. RegisteredNov 12, 2025
  2. Plan review
  3. ConstructionJul '26 – Jul '27
  4. Inspected
  5. Closed
39% through of a 12-month buildJul 1, 2026 → Jul 1, 2027

4 contacts on this project · 2 phone numbers

Permit & project history

1 project
  1. DFW Hangar 4 Slab Repairs

    Install helical piers to raise slab on grade which has settled. project also includes a restroom renovation, replacement of electrical switchgear and feeders, and some site work to address trees and drainage. — hangar 4

    TDLR project registrationRenovation/AlterationReview Complete28,000 sq ft$6.5M est.
    Tenant / owner
    Dfw Hangar 4 Slab Repairs
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 2132 N 16th Ave

What is being built at 2132 N 16th Ave?

The TDLR registration describes repairs and renovations to DFW Hangar 4, not a new building. Work includes slab stabilization, a restroom renovation, electrical equipment replacement, and site work.

What are the DFW Hangar 4 slab repairs?

The project calls for installing helical piers to raise a settled slab on grade. The registration also lists restroom, electrical, and site improvements.

When was the Hangar 4 project registered?

The project was registered on November 12, 2025. Its TDLR project number is TABS2026005668.

How much will the Hangar 4 renovation cost?

The applicant's estimated cost is $6.5 million, according to the TDLR registration. This is an estimate for the project.

How large is the DFW Hangar 4 project?

The TDLR record lists the project at 28,000 square feet.

What electrical work is planned at DFW Hangar 4?

The project description includes replacing electrical switchgear and feeders.