groundranger
Historic · latest filing Feb 2024Commercial

4400 Sterilite Drive

Ennis, TX 75119 · Iko Metals Usa Inc.

IKO Metals factory modifications in Ennis

Modifications to the IKO Metals factory at 4400 Sterilite Drive include concrete work for process equipment, an office and breakroom area, new doorways and driveways, and structural steel for process components. The project was registered with TDLR on February 29, 2024, with about 43,000 square feet of work area; its estimated cost was $2.8 million.

Summarized from Texas Department of Licensing and Regulation records · updated Feb 29, 2024

Projects
1
1 filings
Latest filing
Feb 29, 2024
since Feb 29, 2024
Largest scope
43,000 sf
Estimated cost
$2.8M
state registration

Where this project stands

Inspected · closing out

Modifications to IKO Metals Ennis factory building

43,000 sq ft · $2.8M est.

  1. RegisteredFeb 29, 2024
  2. Plan review
  3. ConstructionMar '24 – Aug '24
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 2 phone numbers

Permit & project history

1 project
  1. Modification of concrete for process equipment, installation of office/breakroom area, new doorways & driveways, and structural steel for process components. approx. 43,000 sq ft of total work area. — iko metals ennis

    TDLR project registrationRenovation/AlterationInspection Complete43,000 sq ft$2.8M est.
    Tenant / owner
    Modifications To Iko Metals Ennis Factory Building
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 4400 Sterilite Drive

What is being built at 4400 Sterilite Drive in Ennis?

The project is a modification of the IKO Metals factory, including concrete for process equipment, an office and breakroom area, new doorways and driveways, and structural steel for process components.

Is a new factory being built at 4400 Sterilite Drive?

The TDLR registration describes modifications to the IKO Metals factory building, not a new factory.

When was the IKO Metals factory project registered?

The project was registered with the Texas Department of Licensing and Regulation on February 29, 2024. Its TDLR project number is TABS2024012689.

How large is the IKO Metals factory modification project?

The registration lists approximately 43,000 square feet of total work area.

How much will the IKO Metals factory modifications cost?

The TDLR registration lists an estimated project cost of $2.8 million.

Are the IKO Metals factory modifications complete?

The TDLR record lists the project status as Inspection Complete.