groundranger
Recent · latest filing Oct 2025Commercial

3800 Long Prairie Rd

Flower Mound, TX 75028 · Ivt Eldorado Marketplace Frisco, LLC

EV charging facility planned at 3800 Long Prairie Road

A new EV charging facility with dispensers and power units is planned for the existing parking lot at 3800 Long Prairie Road. The Texas Department of Licensing and Regulation registration, filed October 8, 2025, lists 2,000 square feet and an applicant-estimated project cost of $500,000.

Summarized from Texas Department of Licensing and Regulation records · updated Oct 8, 2025

Projects
1
1 filings
Latest filing
Oct 8, 2025
since Oct 8, 2025
Largest scope
2,000 sf
Estimated cost
$500K
state registration

Where this project stands

Under construction

TX240458 Flower Mound (Riverwalk Market)

2,000 sq ft · $500K est.

  1. RegisteredOct 8, 2025
  2. Plan review
  3. ConstructionDec '25 – Dec '26
  4. Inspected
  5. Closed
94% through of a 12-month buildDec 15, 2025 → Dec 12, 2026

4 contacts on this project · 4 phone numbers

Permit & project history

1 project
  1. Construct/install new ev charging facility to include dispenser and power units in existing parking lot. — electrify america evcs

    TDLR project registrationNew ConstructionReview Complete2,000 sq ft$500K est.
    Tenant / owner
    Tx240458 Flower Mound (riverwalk Market)
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 3800 Long Prairie Rd

What is being built at 3800 Long Prairie Road in Flower Mound?

A new EV charging facility with dispensers and power units is planned for the existing parking lot. The project is listed in a TDLR registration dated October 8, 2025.

Is Electrify America adding EV chargers near Riverwalk Market?

The TDLR project description identifies Electrify America EV charging equipment at 3800 Long Prairie Road, near Riverwalk Market.

How much will the EV charging project in Flower Mound cost?

The TDLR registration lists an applicant-estimated project cost of $500,000. This is an estimate for the project, not a confirmed final cost.

How large is the planned EV charging facility at 3800 Long Prairie Road?

The TDLR registration lists the project at 2,000 square feet and describes installation in an existing parking lot.

When was the EV charging project near Flower Mound Town Center filed?

The project registration was filed October 8, 2025. The TDLR record lists its status as Review Complete.

Also being built nearby

All of 75028

More parking structures in 75028.

Email me when it passes inspection