4577 Marine Creek Pkwy

Fort Worth, TX 76106 · Marine Creek Parkway Phase 2 At IH-820 Interchange, Quiktrip #1871 Coffeewow

Marine Creek Parkway Phase 2 interchange improvements

Turn lanes, crosswalks, sidewalks, curb ramps, signage and pavement markings are planned at the Marine Creek Parkway and IH-820 frontage-road intersection. The TDLR project registration was filed on February 28, 2025, and lists an applicant-estimated project cost of $319,000.

Summarized from Texas Department of Licensing and Regulation records · updated Feb 28, 2025

Projects
2
2 filings
Latest filing
Feb 28, 2025
since Feb 28, 2025
Largest scope
3,780 sf
Estimated cost
$319K
state registration

Where this project stands

Under construction

Marine Creek Parkway Phase 2 at IH-820 Interchange

3,780 sq ft · $319K est.

  1. RegisteredFeb 28, 2025
  2. Plan review
  3. ConstructionOct '25 – Nov '26
  4. Inspected
  5. Closed
97% through of a 14-month buildOct 1, 2025 → Nov 30, 2026

4 contacts on this project · 3 phone numbers

Permit & project history

2 projects
  1. Installation of turn lanes, crosswalks, sidewalks, curb ramps, signage and pavement markings. 420 sy of prop sidewalk — intersection of marine creek parkway and interstate 820 frontage roads

    TDLR project registrationRenovation/AlterationReview Complete3,780 sq ft$319K est.
    Tenant / owner
    Marine Creek Parkway Phase 2 At IH-820 Interchange
    Design firm
    Pro
    Contact
    Pro
  2. Equipment and millwork modifications to existing coffee bar and lid bar. — quiktrip #1871

    TDLR project registrationRenovation/AlterationProject Closed188 sq ft$60K est.
    Tenant / owner
    Quiktrip #1871 Coffeewow
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 4577 Marine Creek Pkwy

What is being built at 4577 Marine Creek Pkwy?

The Marine Creek Parkway Phase 2 project includes turn lanes, crosswalks, sidewalks, curb ramps, signage and pavement markings at the IH-820 interchange. Its TDLR registration was filed February 28, 2025.

What road improvements are planned at Marine Creek Parkway and IH-820?

The project registration describes turn lanes, crosswalks, sidewalks, curb ramps, signage and pavement markings at the intersection with the IH-820 frontage roads.

When was the Marine Creek Parkway Phase 2 project filed?

The TDLR registration was filed on February 28, 2025. The record lists the project status as Review Complete.

How much will the Marine Creek Parkway interchange project cost?

The TDLR record lists an applicant-estimated cost of $319,000 for the project.

Does the Marine Creek Parkway project include new sidewalks?

Yes. The registration describes sidewalk installation, including 420 square yards of proposed sidewalk.