15101 N Beach Street
Fort Worth, TX 76262 · Alliance Center North No 2 Ltd
Truck gate and safety upgrades at 15101 N Beach Street
A project at the existing distribution facility adds automatic gate arms at the truck guard house, conduit connecting the arms to the guard house, and bollards near an existing generator and an associate building entrance. The TDLR project registration was filed February 22, 2024.
Summarized from Texas Department of Licensing and Regulation records · updated Feb 22, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Feb 22, 2024
- since Feb 22, 2024
- Largest scope
- 774 sf
- Estimated cost
- $964K
- state registration
Where this project stands
Finishing up · inspection next7555-501 DFW2
774 sq ft · $964K est.
- RegisteredFeb 22, 2024
- Plan review
- ConstructionMar '24 – May '24
- Inspectednow
- Closed
Scheduled to finish May 10, 2024; the state inspection hasn't been filed yet.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectThe addition of automatic gate arms at the existing truck guard house located at an existing distribution facility. boring conduit from gate arms back to guard house. installing bollards around existing generator and at associate building entrance — 7555
TDLR project registrationRenovation/AlterationReview Complete774 sq ft$964K est.- Project #
- TABS2024012184
- Tenant / owner
- 7555-501 Dfw2
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 15101 N Beach Street
What is being built at 15101 N Beach Street?
The project adds automatic gate arms at the existing truck guard house, conduit, and bollards at the existing distribution facility. It is a renovation and alteration, not a new distribution facility.
When was the project at 15101 N Beach Street filed?
The TDLR project registration was filed February 22, 2024. The record is TABS2024012184.
What are the gate arms for at 15101 N Beach Street?
The registration describes automatic gate arms at the facility’s existing truck guard house, with conduit bored back to the guard house.
Are bollards being installed at 15101 N Beach Street?
Yes. The project description includes bollards around an existing generator and at an associate building entrance.
How much is the 15101 N Beach Street project estimated to cost?
The TDLR registration lists an applicant-estimated project cost of $963,741. This is an estimate, not a reported final cost.
What is being changed near Bell - Advanced Manufacturing Center?
About 384 meters from the center, a TDLR registration describes gate arms, conduit, and bollards at an existing distribution facility at 15101 N Beach Street. The project was filed February 22, 2024.