1200 Block Of Lipscomb St. & Forest St
Grapevine, TX 76051 · City Of Grapevine
Forest and Lipscomb street and utility improvements
The City of Grapevine registered a project for road and utility improvements at Forest Street and Lipscomb Street on April 16, 2025. The scope includes 800 feet of asphalt roadway with curb, gutter and sidewalk, plus storm drain, water line and sewer line improvements and replacements; the TDLR registration lists an estimated cost of $1.5 million.
Summarized from Texas Department of Licensing and Regulation records · updated Apr 16, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Apr 16, 2025
- since Apr 16, 2025
- Largest scope
- 4,000 sf
- Estimated cost
- $1.5M
- state registration
Where this project stands
Inspected · closing outPaving and Utility Improvement for Forest St. & Lipscomb St.
4,000 sq ft · $1.5M est.
- RegisteredApr 16, 2025
- Plan review
- ConstructionJun '25 – Mar '26
- Inspected
- Closednow
The building is substantially done. Move-in, fit-out and service work usually follow.
4 contacts on this project · 3 phone numbers
Permit & project history
1 project800 lf asphalt roadway with curb and gutter and sidewalk. internal storm drain, water line, and sewer line improvements and replacements. (sq ft;4000) — n/a
TDLR project registrationNew ConstructionInspection Complete4,000 sq ft$1.5M est.- Project #
- TABS2025016757
- Tenant / owner
- Paving And Utility Improvement For Forest St. & Lipscomb St.
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 1200 Block Of Lipscomb St. & Forest St
What is being built at Forest Street and Lipscomb Street in Grapevine?
A City of Grapevine project covers roadway and utility improvements, including 800 feet of asphalt road, curb, gutter and sidewalk, along with storm drain, water and sewer work. The TDLR project registration was filed April 16, 2025.
What is the project at the 1200 block of Lipscomb Street and Forest Street?
The project is for paving and utility improvements. Its scope includes roadway work and improvements or replacements to storm drain, water and sewer lines.
What's being built near the City of Grapevine on Shady Brook Drive?
The Forest Street and Lipscomb Street project is about 441 meters from the City of Grapevine location at 602 Shady Brook Drive. It covers roadway and utility improvements.
What is the estimated cost of the Forest and Lipscomb street project?
The TDLR registration lists an estimated project cost of $1.5 million. This is the applicant's estimate for the project.
When was the Forest Street and Lipscomb Street project filed?
The TDLR project registration, number TABS2025016757, was filed April 16, 2025.
Is the Forest and Lipscomb street project complete?
The TDLR record lists the status as “Inspection Complete.”
Also being built nearby
All of 76051- 602 Shady Brook Drive · City Of GrapevineAug 4, 2025Grapevine wwtp administration facilities improvements — new construction — new 6,982sf administration building, including laboratory, control room and administrative spaces. new 3,527 sq ft maintenance building including maintenance bay and storage spaces · 441 m away
- 1206 W Northwest Highway · W.c. Lucas DivisionMar 26, 2025Daytrip diner — renovation/alteration — cosmetic alterations to an existing restaurant space. the scope includes selective demolition, interior renovations, and installation of new finishes, equipment, and furnishings to modernize the establishment · 548 m away