407 Fairwinds Street

Hallettsville, TX 77964 · Grafe & Janecek Properties LLC

Two EV chargers planned at Grafe Chevrolet GMC in Hallettsville

A Texas Department of Licensing and Regulation project registration describes placing two EV chargers at Grafe Chevrolet GMC in Hallettsville. The registration was filed June 25, 2026, and lists a 50-square-foot project area, excluding utility work.

Summarized from Texas Department of Licensing and Regulation records · updated Jun 25, 2026

Projects
1
1 filings
Latest filing
Jun 25, 2026
since Jun 25, 2026
Largest scope
50 sf
Estimated cost
$7.5M
state registration

Where this project stands

Finishing up · inspection next

GRAFE CHEVROLET GMC Halletsville TX Equipment + Turnkey

50 sq ft · $7.5M est.

  1. RegisteredJun 25, 2026
  2. Plan review
  3. ConstructionJul '26 – Jul '26
  4. Inspectednow
  5. Closed

Scheduled to finish Jul 17, 2026; the state inspection hasn't been filed yet.

4 contacts on this project · 2 phone numbers

Permit & project history

1 project
  1. Placing 2 ev chargers 50 foot space excluding utility work — halletsville gmc

    TDLR project registrationAdditions to Existing BuildingReview Complete50 sq ft$7.5M est.
    Tenant / owner
    Grafe Chevrolet Gmc Halletsville TX Equipment + Turnkey
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 407 Fairwinds Street

What is being built at 407 Fairwinds Street in Hallettsville?

A TDLR project registration describes placing two EV chargers at Grafe Chevrolet GMC. It lists a 50-square-foot project area, excluding utility work.

Is Grafe Chevrolet GMC in Hallettsville getting EV chargers?

A June 25, 2026, TDLR registration describes a project to place two EV chargers at the dealership.

When was the EV charger project at 407 Fairwinds Street filed?

The TDLR registration was filed June 25, 2026. Its status is listed as Review Complete.

How many EV chargers are planned at Grafe Chevrolet GMC?

The project description says two EV chargers will be placed at the Hallettsville dealership.

How large is the EV charger project at 407 Fairwinds Street?

The TDLR registration lists 50 square feet, excluding utility work.