groundranger
Historic · latest filing Nov 2024Commercial

2400 E. Jefferson Ave

Harlingen, TX 78550 · Harlingen Cosolidated Independent School District

Bonham Elementary to get two asphalt basketball courts

A 100-by-94-foot asphalt area for two basketball courts with striping was registered for upgrades at Bonham Elementary, 2400 E. Jefferson Ave. The TDLR project registration was filed November 21, 2024, and lists the project as closed.

Summarized from Texas Department of Licensing and Regulation records · updated Nov 21, 2024

Projects
1
1 filings
Latest filing
Nov 21, 2024
since Nov 21, 2024
Largest scope
9,400 sf
Estimated cost
$85K
state registration

Where this project stands

Completed

Harlingen CISD Bonham Elementary Playground Upgrades

9,400 sq ft · $85K est.

  1. RegisteredNov 21, 2024
  2. Plan review
  3. ConstructionDec '24 – Mar '25
  4. Inspected
  5. Closed

Ran as a 3-month build.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Remove existing caliche and installed a 100' x 94' asphalt paving for two basketball courts worh stripping. — bonham elementary

    TDLR project registrationRenovation/AlterationProject Closed9,400 sq ft$85K est.
    Tenant / owner
    Harlingen Cisd Bonham Elementary Playground Upgrades
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 2400 E. Jefferson Ave

What is being built at 2400 E. Jefferson Ave. in Harlingen?

The project at Bonham Elementary calls for asphalt paving for two basketball courts, with striping. The registered area is 100 by 94 feet.

Is Bonham Elementary getting new basketball courts?

A TDLR registration describes upgrades that include paving for two basketball courts at Bonham Elementary. It says existing caliche will be removed before the asphalt is installed.

When was the Bonham Elementary playground project registered?

The TDLR registration was filed November 21, 2024. The project is listed as closed.

How much is the Bonham Elementary court project expected to cost?

The TDLR registration lists an estimated project cost of $85,000.

How large is the Bonham Elementary basketball court area?

The registered asphalt paving area is 100 by 94 feet, or 9,400 square feet.

What is the project number for Bonham Elementary playground upgrades?

The TDLR project registration number is TABS2025006120. It was filed November 21, 2024.