groundranger
Recent · latest filing Jun 2026Commercial

1301 Fannin Level 9

Houston, TX 77002 · 1301 Fannin Level 9 Data Center Reno, 1301 Fannin Restroom Renovation- Level 9

Level 9 data center renovation at 1301 Fannin

A Level 9 data center renovation at the multi-tenant building at 1301 Fannin includes relocating a corridor wall and data machinery, adding a temporary interior wall, and modifying piping above the plenum. The project was registered with TDLR on June 3, 2026, under project number TABS2026021950; the applicant's estimated project cost is $1,768,623.

Summarized from Texas Department of Licensing and Regulation records · updated Jun 3, 2026

Projects
2
2 filings
Latest filing
Jun 3, 2026
since Sep 24, 2025
Largest scope
1,020 sf
Estimated cost
$1.8M
state registration

Where this project stands

Finishing up · inspection next

1301 FANNIN LEVEL 9 DATA CENTER RENO

1,020 sq ft · $1.8M est.

  1. RegisteredJun 3, 2026
  2. Plan review
  3. ConstructionJun '26 – Aug '26
  4. Inspectednow
  5. Closed

Scheduled to finish Aug 1, 2026; the state inspection hasn't been filed yet.

4 contacts on this project · 3 phone numbers

Permit & project history

2 projects
  1. Relocation of corridor wall and addition of temporary interior wall at data center for relocation of data machinery. partial reno of piping above plenum to tie-in to new machinery. — netrality

    TDLR project registrationRenovation/AlterationReview Complete1,020 sq ft$1.8M est.
    Tenant / owner
    1301 Fannin Level 9 Data Center Reno
    Design firm
    Pro
    Contact
    Pro
  2. Interior remodel of tenant use restrooms including plumbing & interior finishes. — netrality

    TDLR project registrationRenovation/AlterationProject Closed460 sq ft$180K est.
    Tenant / owner
    1301 Fannin Restroom Renovation- Level 9
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 1301 Fannin Level 9

What is being built at 1301 Fannin Level 9?

The TDLR registration describes a renovation of a data center, including work to relocate data machinery, move a corridor wall, and tie piping into the new machinery. It was filed June 3, 2026, as project TABS2026021950.

Is a new data center being built at 1301 Fannin?

The registration describes renovations to an existing Level 9 data center, not construction of a new building. The work includes interior wall and piping changes for relocated data machinery.

How much will the 1301 Fannin Level 9 renovation cost?

The applicant's estimated cost for the data center renovation is $1,768,623, according to TDLR project TABS2026021950. This is an estimate, not a confirmed final cost.

What work was planned for the restrooms at 1301 Fannin?

A separate Level 9 project was registered September 24, 2025, to remodel tenant-use restrooms, including plumbing and interior finishes. TDLR lists it as project TABS2026001725.

What's being renovated near Sandbox VR on San Jacinto?

A Level 9 data center renovation is registered at 1301 Fannin, about 40 meters from Sandbox VR at 1201 San Jacinto Street. The registration was filed June 3, 2026.

Is 1301 Fannin a single-tenant building?

The records identify 1301 Fannin as a multi-tenant building. The described data center and restroom work is specific to Level 9.

Also being built nearby

All of 77002
Email me when it passes inspection