groundranger
Recent · latest filing Jun 2025Commercial

222 West Crosstimbers Street

Houston, TX 77018 · City Of Houston

Houston Fire Station 31 addition and renovations

A 12,254-square-foot addition and major renovations are planned for Houston Fire Station 31 at 222 West Crosstimbers Street. The project was registered with TDLR on June 3, 2025, and includes fire-safety upgrades, new living and sleeping areas, and site improvements. The applicant’s estimated project cost is $4.8 million.

Summarized from Texas Department of Licensing and Regulation records · updated Jun 3, 2025

Projects
1
1 filings
Latest filing
Jun 3, 2025
since Jun 3, 2025
Largest scope
12,254 sf
Estimated cost
$4.8M
state registration

Where this project stands

In state plan review

City of Houston Fire Station 31

12,254 sq ft · $4.8M est.

  1. RegisteredJun 3, 2025
  2. Plan reviewnow
  3. ConstructionOct '25 – Jul '26
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. New addition & major renovations to fire station 31. included are life safety items/new fire sprinkler/new living/sleeping areas,& site upgrades — houston fire department fire station 31

    TDLR project registrationAdditions to Existing BuildingProject Registered12,254 sq ft$4.8M est.
    Tenant / owner
    City Of Houston Fire Station 31
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 222 West Crosstimbers Street

What is being built at 222 West Crosstimbers Street?

The project is an addition and major renovation of Houston Fire Station 31. The June 3, 2025 TDLR registration describes fire-safety work, new living and sleeping areas, and site upgrades.

Is a new fire station being built on West Crosstimbers?

The TDLR record describes an addition and major renovations to the existing Houston Fire Station 31, not a new station.

When was the Fire Station 31 project registered?

The project was registered with TDLR on June 3, 2025, under project number TABS2025020427.

How large is the Fire Station 31 project?

The registered project is listed as 12,254 square feet.

How much will the Fire Station 31 renovations cost?

The applicant’s estimated cost for the project is $4.8 million. This is an estimate, not a final reported construction cost.

What is being built near Kroozin on West Crosstimbers?

At 222 West Crosstimbers Street, near Kroozin at 125 Crosstimbers Street, the registered project is an addition and major renovation to Houston Fire Station 31. It was registered on June 3, 2025.

Also being built nearby

All of 77018
Email me when plan review is complete