Port of Houston coordination center planned at Turning Basin
A new two-story Port Coordination Center facility is planned at 111 East Loop North, with a connected garage and apparatus bay. The Texas Department of Licensing and Regulation registration was filed April 3, 2024, and describes a 35,257-square-foot building.
Summarized from Texas Department of Licensing and Regulation records · updated Apr 3, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Apr 3, 2024
- since Apr 3, 2024
- Largest scope
- 35,257 sf
- Estimated cost
- $13M
- state registration
Where this project stands
Finishing up · inspection nextConstruct New Port Coordination Center Facility at the Turning Basin
35,257 sq ft · $13M est.
- RegisteredApr 3, 2024
- Plan review
- ConstructionAug '24 – Sep '26
- Inspectednow
- Closed
Scheduled to finish Sep 1, 2026; the state inspection hasn't been filed yet.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectNew 2-story concrete tilt-wall office building and connected garage/apparatus bay. 35,257 sq feet. — port of houston - port coordination center
TDLR project registrationNew ConstructionReview Complete35,257 sq ft$13M est.- Project #
- TABS2024015306
- Tenant / owner
- Construct New Port Coordination Center Facility At The Turning Basin
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 111 East Loop North
What is being built at 111 East Loop North?
A new two-story office building for the Port of Houston’s Port Coordination Center, connected to a garage and apparatus bay. The project is listed as new construction.
When was the Port Coordination Center project registered?
The TDLR project registration was filed April 3, 2024. Its registration number is TABS2024015306.
How large will the Port Coordination Center facility be?
The TDLR registration describes a 35,257-square-foot facility.
Who is listed for the Port Coordination Center project?
The Port of Houston Authority is listed as the owner or occupant for the project.
What is the estimated cost of the Port Coordination Center?
The TDLR registration lists an estimated project cost of $13 million. This is the applicant’s estimate.
What type of construction is planned for the facility?
The registration describes a two-story concrete tilt-wall office building with a connected garage and apparatus bay.