Server rooms planned at 9625 Fallbrook Pines Drive

A 22,541-square-foot addition for server containment rooms and an electrical room is planned at 9625 Fallbrook Pines Drive. The Texas Department of Licensing and Regulation registered the project on May 21, 2024, under project number TABS2024019010. The applicant estimated the project cost at $50 million.

Summarized from Texas Department of Licensing and Regulation records · updated May 21, 2024

Projects
1
1 filings
Latest filing
May 21, 2024
since May 21, 2024
Largest scope
22,541 sf
Estimated cost
$50M
state registration

Where this project stands

In state plan review

Megawatt Fallbrook Phase 2

22,541 sq ft · $50M est.

  1. RegisteredMay 21, 2024
  2. Plan reviewnow
  3. ConstructionJun '24 – Feb '25
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 2 phone numbers

Permit & project history

1 project
  1. The scope of work inlcudes 3 air conditioned rooms that will house server containment rooms as well as an electrical room as an accessory to the server rooms. mechanical chiller area on site will be design build and is not in architectural scope. — 9625 fallbrook pines

    TDLR project registrationAdditions to Existing BuildingProject Registered22,541 sq ft$50M est.
    Tenant / owner
    Megawatt Fallbrook Phase 2
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 9625 Fallbrook Pines Drive

What is being built at 9625 Fallbrook Pines Drive?

A registered project calls for a 22,541-square-foot addition with three air-conditioned server containment rooms and an electrical room. The mechanical chiller area is not included in the architectural scope.

When was the project at 9625 Fallbrook Pines Drive registered?

The Texas Department of Licensing and Regulation registered the project on May 21, 2024. Its project number is TABS2024019010.

How large is the Fallbrook Pines Drive addition?

The registered project lists 22,541 square feet of additions to an existing building.

What will the new rooms at 9625 Fallbrook Pines Drive be used for?

The project description says three air-conditioned rooms will house server containment rooms, with an electrical room as an accessory.

How much will the project at 9625 Fallbrook Pines Drive cost?

The applicant's TDLR estimate for the project is $50 million. This is an estimate, not a confirmed final cost.