4200 County Road 132
Hutto, TX 78634 · Skybox - Hutto 2 Fit Up, Skybox - Hutto 2 Fit Out + 3 more
Data center construction and fit-outs at Hutto site
TDLR registrations indicate a multi-tenant data center site at 4200 County Road 132, including a new 235,730-square-foot Building 2 core and shell registered on April 3, 2024. Registrations in August and September 2025 describe interior fit-out and building-owner improvements to Building 2, while a January 2024 registration covers interior improvements to Building 1.
Summarized from Texas Department of Licensing and Regulation records · updated Sep 19, 2025
- Projects
- 5
- 5 filings
- Latest filing
- Sep 19, 2025
- since Jan 31, 2024
- Largest scope
- 235,730 sf
- Estimated cost
- $470M
- state registration
Where this project stands
In state plan reviewSkybox - Hutto 2 Fit Up
234,820 sq ft · $470M est.
- RegisteredSep 19, 2025
- Plan reviewnow
- ConstructionOct '25 – Oct '26
- Inspected
- Closed
Design is filed with the state. Subcontractors and suppliers are usually picked around now.
4 contacts on this project · 3 phone numbers
Permit & project history
5 projectsInterior building improvements for the building owners operations scope. scope includes security offices, conference rooms, loading dock, restrooms, miscellaneous mep support, and data center interior shell walls. 234,820 sq ft — building 2
TDLR project registrationRenovation/AlterationProject Registered234,820 sq ft$470M est.- Project #
- TABS2026001377
- Tenant / owner
- Skybox - Hutto 2 Fit Up
- Design firm
- Pro
- Contact
- Pro
Interior building improvements for the tenants fit out scope. scope includes hot aisle containment for the project's data center cabinets, electrical busways feeding dc cabinets, cable tray routing, and second story office space, 234,820 sq ft — building 2
TDLR project registrationRenovation/AlterationProject Registered234,820 sq ft$125M est.- Project #
- TABS2025026905
- Tenant / owner
- Skybox - Hutto 2 Fit Out
- Design firm
- Pro
- Contact
- Pro
Site improvements & construction of a new core & shell building with a future use as a data center. the proposed project has a two story office & a one story data center shell scope, 235,730 sq ft — building 2
TDLR project registrationNew ConstructionProject Registered235,730 sq ft$78M est.- Project #
- TABS2024015381
- Tenant / owner
- Skybox - Hutto 2 Core/Shell
- Design firm
- Pro
- Contact
- Pro
Interior improvements to an existing,235,730 sq ft data center shell building. scope will include finish walls / ceilings / floors for the use as a data center building. — building 1
TDLR project registrationNew ConstructionProject Registered235,730 sq ft$149M est.- Project #
- TABS2024010542
- Tenant / owner
- Skybox - Hutto 1 Initial Improvements
- Design firm
- Pro
- Contact
- Pro
Site improvements & construction of a new core & shell building with a future use as a data center. the proposed project has a two story office & a one story data center shell scope, 235,730 sq ft — building 1
TDLR project registrationNew ConstructionProject Registered253,730 sq ft$86M est.- Project #
- TABS2024003524
- Tenant / owner
- Skybox - Hutto 1
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 4200 County Road 132
What is being built at 4200 County Road 132 in Hutto?
TDLR records describe a multi-tenant data center site with two buildings. Building 2 is a new core-and-shell project, with later registrations for interior fit-out and building-owner improvements.
What's being built at Hutto Data Center Campus?
Records for the campus at 4200 County Road 132 describe data center construction and interior improvements. Building 2's core-and-shell project was registered on April 3, 2024, under TDLR number TABS2024015381.
How large is the new Building 2 at the Hutto data center?
The core-and-shell registration lists Building 2 at 235,730 square feet. The later fit-out and owner-improvement registrations each list 234,820 square feet.
What work is planned inside Building 2?
The August 28, 2025 registration describes data center cabinet containment, electrical busways, cable trays, and second-story office space. The September 19, 2025 registration includes security offices, conference rooms, loading-dock areas, restrooms, and data center shell walls.
Are there improvements planned for Building 1 at 4200 County Road 132?
Yes. A TDLR registration dated January 31, 2024, describes interior improvements to an existing 235,730-square-foot data center shell, including finished walls, ceilings, and floors.
What is the estimated cost of the Hutto data center project?
The fact sheet lists a TDLR estimated cost of $470 million for the project. This is an estimate, not a reported final project cost.