Ingram, TX 78025 · Ingram Hs Science Classroom And Lab Wing Addition, Ingram Hs Softball Field Complex

Ingram High School classroom, lab and softball projects

TDLR records describe two projects at the Ingram High School site: a classroom, science lab and art room addition registered on November 12, 2024, and a softball field complex registered on November 21, 2023. The addition is listed at 9,841 square feet and includes restrooms and support spaces.

Summarized from Texas Department of Licensing and Regulation records · updated Nov 12, 2024

Projects
2
2 filings
Latest filing
Nov 12, 2024
since Nov 12, 2024
Largest scope
9,841 sf
Estimated cost
$3.8M
state registration

Where this project stands

Finishing up · inspection next

Ingram HS Science Classroom and Lab Wing Addition

9,841 sq ft · $3.8M est.

  1. RegisteredNov 12, 2024
  2. Plan review
  3. ConstructionNov '24 – Aug '25
  4. Inspectednow
  5. Closed

Scheduled to finish Aug 29, 2025; the state inspection hasn't been filed yet.

4 contacts on this project · 2 phone numbers

Permit & project history

2 projects
  1. The addition of 2 classrooms, 2 science labs, and an art room, along with restrooms and support spaces. the new addition will be constructed of concrete slab on grade, pre-engineered metal building, metal roof and eifs. utilities will be extended. — ingram hs science classroom and lab wing addition

    TDLR project registrationAdditions to Existing BuildingReview Complete9,841 sq ft$3.8M est.
    Tenant / owner
    Ingram Hs Science Classroom And Lab Wing Addition
    Design firm
    Pro
    Contact
    Pro
  2. New softball field with a ticket booth, concessions, restrooms, dugouts, and press box. sitework will include new utilities, fencing, and retaining walls. — ingram hs softball field complex

    TDLR project registrationNew ConstructionProject Closed1,200 sq ft$1.2M est.
    Tenant / owner
    Ingram Hs Softball Field Complex
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 510 TX-39

What is being built at 510 TX-39 in Ingram?

TDLR records list a school building addition and a separate softball field complex at the site. The addition was registered on November 12, 2024, and the softball project on November 21, 2023.

What classrooms are included in the Ingram High School addition?

The addition includes two classrooms, two science labs, an art room, restrooms and support spaces. TDLR registration TABS2025005372 lists 9,841 square feet.

Is a new softball field planned at Ingram High School?

A TDLR record describes a new softball field complex with a ticket booth, concessions, restrooms, dugouts and a press box. The project was registered on November 21, 2023, as TABS2024005894.

How large is the Ingram High School classroom and lab addition?

The addition is listed at 9,841 square feet in TDLR record TABS2025005372, dated November 12, 2024.

What is the estimated cost of the Ingram High School addition?

The applicant's estimated cost for the classroom and lab addition is $3,825,000, according to TDLR record TABS2025005372.

Are the softball field and classroom addition one project?