Laredo, TX 78045 · Midwest Sterilization Corporation

Midwest Sterilization adds process-support buildings in Laredo

TDLR registrations describe new buildings and equipment to support mechanical and process upgrades at Midwest Sterilization Corporation’s Laredo ethylene oxide sterilization operations. The projects were registered on June 28, 2024, and March 3, 2025; both are listed as inspection complete.

Summarized from Texas Department of Licensing and Regulation records · updated Mar 3, 2025

Projects
2
2 filings
Latest filing
Mar 3, 2025
since Jun 28, 2024
Largest scope
7,600 sf
Estimated cost
$20M
state registration

Where this project stands

Inspected · closing out

Scrubber-Polishing

745 sq ft · $3.5M est.

  1. RegisteredMar 3, 2025
  2. Plan review
  3. ConstructionJun '25 – Oct '25
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 2 phone numbers

Permit & project history

2 projects
  1. Scrubber-Polishing

    The project contains architectural scope required to support mechanical and process upgrades to the sterilization operations. new building with new fans and electrical work will be installed. — midwest sterilization corporation

    TDLR project registrationNew ConstructionInspection Complete745 sq ft$3.5M est.
    Tenant / owner
    Pro
    Design firm
    Pro
    Contact
    Pro
  2. The project contains architectural scope as required to support mechanical and process upgrades to midwest’s laredo,tx ethylene oxide sterilization operations, outbuildings to house equipment installed as part of the mechanical and process upgrades. — midwest sterilization

    TDLR project registrationNew ConstructionInspection Complete7,600 sq ft$20M est.
    Tenant / owner
    Fugitive Emission Project Phase 2
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 12010 General Milton Dr

What is being built at 12010 General Milton Dr?

TDLR records describe outbuildings and a new building with fans and electrical work to support process upgrades at Midwest Sterilization Corporation’s sterilization operations. The registrations are for new construction.

What is the Scrubber-Polishing project in Laredo?

The project registration describes a new building with fans and electrical work supporting mechanical and process upgrades. It was filed on March 3, 2025, under TDLR number TABS2025013131, and is listed as inspection complete.

What is the Fugitive Emission Project Phase 2?

The project covers outbuildings to house equipment for mechanical and process upgrades to Midwest Sterilization’s ethylene oxide sterilization operations. It was registered on June 28, 2024, as TDLR project TABS2024021942 and is listed as inspection complete.

How much are the Laredo sterilization projects estimated to cost?

The TDLR registration for Fugitive Emission Project Phase 2 lists an estimated cost of $20 million. The Scrubber-Polishing registration lists $3.5 million; these are project estimates, not a combined total.

What's being built near Killam Development on General Milton Drive?

About 397 meters from Killam Development at 9001 Killam Industrial Boulevard, TDLR records describe new construction supporting Midwest Sterilization Corporation’s process upgrades at 12010 General Milton Dr.

Are the projects at 12010 General Milton Dr complete?

Both TDLR project registrations are listed as inspection complete. The records do not give a separate completion date.

Also being built nearby

All of 78045
Email me when the project is closed