300 Treatment Plant Road
Levelland, TX 79336 · City Of Levelland
Levelland plans a new 1.8 MGD wastewater treatment plant
A new mechanical wastewater treatment plant is planned at 300 Treatment Plant Road in Levelland. The City of Levelland’s TDLR project registration, filed August 21, 2025, describes closing the existing aeration lagoons and building the new plant. The applicant’s estimated project cost is $20 million.
Summarized from Texas Department of Licensing and Regulation records · updated Aug 21, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Aug 21, 2025
- since Aug 21, 2025
- Largest scope
- 5,628 sf
- Estimated cost
- $20M
- state registration
Where this project stands
Under constructionCity of Levelland New 1.8 MGD Wastewater Treatment Plant
5,628 sq ft · $20M est.
- RegisteredAug 21, 2025
- Plan review
- ConstructionMay '25 – Dec '26
- Inspected
- Closed
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectClosing of existing aeration lagoons and construction of a new mechanical plant which includes: screening, aeration basins, clarifiers, disinfection equipment, irrigation pump station, sludge dewatering equipment and disposal methods. — levelland wastewater treatment plant
TDLR project registrationNew ConstructionReview Complete5,628 sq ft$20M est.- Project #
- TABS2025026401
- Tenant / owner
- City Of Levelland New 1.8 Mgd Wastewater Treatment Plant
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 300 Treatment Plant Road
What is being built at 300 Treatment Plant Road in Levelland?
A new mechanical wastewater treatment plant is planned at the site. The City of Levelland registered the project with TDLR on August 21, 2025, under project number TABS2025026401.
What will the new Levelland wastewater treatment plant include?
The project description lists screening, aeration basins, clarifiers, disinfection equipment, an irrigation pump station, and sludge dewatering and disposal equipment.
What is the capacity of the new Levelland wastewater treatment plant?
The project is named the City of Levelland New 1.8 MGD Wastewater Treatment Plant, indicating a planned capacity of 1.8 million gallons per day.
How much will the new Levelland wastewater treatment plant cost?
The applicant’s estimated cost for the project is $20 million, according to the TDLR registration filed August 21, 2025.
What is planned for the existing aeration lagoons at the Levelland treatment plant?
The project description says the existing aeration lagoons will be closed as part of the project.