2501 Edmonds Lane
Lewisville, TX 75067 · Digital Realty
DFW44 data center to add a fourth data hall
TDLR records show a shell addition for a future fourth data hall at the existing DFW44 data center, registered September 24, 2026. A separate registration dated May 4, 2026, covers buildout and equipment for one data center suite in the building. The applicant’s estimated project cost is $74.6 million.
Summarized from Texas Department of Licensing and Regulation records · updated Sep 24, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Sep 24, 2026
- since May 4, 2026
- Largest scope
- 43,607 sf
- Estimated cost
- $75M
- state registration
Where this project stands
In state plan reviewProject Gold Phase 2 DFW44
43,607 sq ft · $20M est.
- RegisteredSep 24, 2026
- Plan reviewnow
- ConstructionJan '27 – Oct '27
- Inspected
- Closed
Construction is scheduled to start Jan 5, 2027. Subcontractors and suppliers are usually picked in the weeks before.
4 contacts on this project · 3 phone numbers
Permit & project history
2 projectsShell addition of the future data hall 4 to the existing dfw44 data center building. — dfw44
TDLR project registrationAdditions to Existing BuildingProject Registered43,607 sq ft$20M est.- Project #
- TABS2027001867
- Tenant / owner
- Project Gold Phase 2 Dfw44
- Design firm
- Pro
- Contact
- Pro
Build out and equipment fit out of one data center suite within the existing dfw44 data center building. — dfw44
TDLR project registrationRenovation/AlterationProject Registered37,370 sq ft$75M est.- Project #
- TABS2026019308
- Tenant / owner
- Project Gold Phase 2 - Dfw44
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 2501 Edmonds Lane
What is being built at 2501 Edmonds Lane?
TDLR records describe a shell addition for a future data hall 4 at the existing DFW44 data center. The addition is listed as 43,607 square feet.
Is a new data center being built at 2501 Edmonds Lane?
The records describe an addition to an existing data center, not a new standalone data center. They also list buildout and equipment for one data center suite within the existing building.
When was the DFW44 data hall addition registered?
The TDLR project registration for the shell addition is dated September 24, 2026. Its registration number is TABS2027001867.
What is the other project registered at DFW44?
A May 4, 2026, TDLR registration covers the buildout and equipment fit-out of one data center suite in the existing building. The registration number is TABS2026019308.
How large is the DFW44 addition?
The registered shell addition for the future fourth data hall is listed at 43,607 square feet.
What is the estimated cost of the DFW44 project?
The applicant’s estimated cost for the project is $74.6 million. This is an estimate, not a confirmed final project cost.