New LISD high school softball building planned in Lumberton

A new 1,531-square-foot concessions, restroom, locker room and press box building is planned at 103 South L.H.S. Drive in Lumberton. The TDLR project registration, filed May 7, 2025, describes demolishing the existing building and constructing a replacement. The applicant’s estimated project cost is $934,000.

Summarized from Texas Department of Licensing and Regulation records · updated May 7, 2025

Projects
1
1 filings
Latest filing
May 7, 2025
since May 7, 2025
Largest scope
1,531 sf
Estimated cost
$934K
state registration

Where this project stands

Finishing up · inspection next

22408 LISD HS Softball Building

1,531 sq ft · $934K est.

  1. RegisteredMay 7, 2025
  2. Plan review
  3. ConstructionJun '25 – Jan '26
  4. Inspectednow
  5. Closed

Scheduled to finish Jan 7, 2026; the state inspection hasn't been filed yet.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Demolition of existing concessions/restroom/locker room/press box building and construction of new concessions/restroom/locker room/press box building. 1,531 sq ft — lisd hs softball budingil

    TDLR project registrationNew ConstructionReview Complete1,531 sq ft$934K est.
    Tenant / owner
    22408 Lisd Hs Softball Building
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 103 South L.h.s. Drive

What is being built at 103 South L.H.S. Drive in Lumberton?

A new building for concessions, restrooms, locker rooms and a press box is planned for the LISD high school softball site. The TDLR registration describes demolishing the existing building and constructing a replacement.

Is the existing softball building being demolished?

Yes. The project registration says the existing concessions, restroom, locker room and press box building will be demolished and replaced.

How large will the new softball building be?

The TDLR registration lists the new building at 1,531 square feet.

When was the Lumberton softball building project registered?

The TDLR project registration was filed May 7, 2025. Its listed status is Review Complete.

What is the estimated cost of the new LISD softball building?

The applicant’s TDLR estimate for the project is $934,000.