New administrative building planned for Wild Horse WWTP
A 5,141-square-foot administrative building is planned as part of the Wild Horse WWTP Expansion at 10621 Blue Bluff Rd. The TDLR project registration was filed May 19, 2025, and describes new construction with maintenance space, offices and bathrooms on the first level, plus an equipment platform on the second level.
Summarized from Texas Department of Licensing and Regulation records · updated May 19, 2025
- Projects
- 1
- 1 filings
- Latest filing
- May 19, 2025
- since May 19, 2025
- Largest scope
- 5,141 sf
- Estimated cost
- $4.1M
- state registration
Where this project stands
Finishing up · inspection nextWild Horse WWTP Expansion
5,141 sq ft · $4.1M est.
- RegisteredMay 19, 2025
- Plan review
- ConstructionMay '25 – Mar '26
- Inspectednow
- Closed
Scheduled to finish Mar 1, 2026; the state inspection hasn't been filed yet.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectA new administrative building. first level includes maintenance area, offices and bathrooms. second level is an equipment platform for electrical and hvac equipment. — administration building
TDLR project registrationNew ConstructionReview Complete5,141 sq ft$4.1M est.- Project #
- TABS2025019252
- Tenant / owner
- Wild Horse Wwtp Expansion
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 10621 Blue Bluff Rd
What is being built at 10621 Blue Bluff Rd in Manor?
A new administrative building is planned for the Wild Horse WWTP Expansion. The TDLR registration, filed May 19, 2025, lists it as new construction under project number TABS2025019252.
What will the new building at the Wild Horse WWTP include?
The first level is described as including a maintenance area, offices and bathrooms. The second level is an equipment platform for electrical and HVAC equipment.
How large is the Wild Horse WWTP administrative building?
The TDLR registration lists the building at 5,141 square feet.
When was the project at 10621 Blue Bluff Rd filed?
The project registration was filed on May 19, 2025. Its listed status is Review Complete.
How much is the Wild Horse WWTP project estimated to cost?
The TDLR registration lists an estimated cost of $4.1 million for the project. This is the applicant's estimate, not a confirmed final cost.
Is the project a new building or a renovation?
The TDLR registration describes it as new construction of an administrative building.
Also being built nearby
All of 78653- 11001 Parmer LnNov 6, 2026Wildhorse retail center (with r sp-2023-0446c) · 302 m away
- 10350 Blue Bluff RdMay 11, 2026**emergency permit needed- apart complex alta wildhorse ranch building 18 unit #18105- meter # ae 7440206** per notes ec only replaced meter jaws to one unit. -hyatt · 358 m away
- 10925-1/2 Parmer LnAug 22, 2022Wildhorse flats · 389 m away
- 10408 Choctaw Print WayJan 22, 2024Install new 7.04kw roof mounted solar system for existing residential only. bluebonnet utility · 424 m away
- 10346 Blue Bluff RdSep 27, 2024130 blue bluff phase i · 435 m away
- 11003 Strawberry Roan DrJan 30, 2025Installation of (19) panasonic panels with (1) panasonic inverter and (2) panasonic batteries - bluebonnett · 443 m away
- 10709 Charger WayMar 20, 2024Installation of solar panels and batteries · 481 m away
- 10503-1/2 Blue Bluff RdJan 31, 2022Northeast interim wastewater treatment plant - reallignment of access drive · 518 m away
- 10505-1/2 Blue Bluff RdDec 5, 2024Blue bluff east · 540 m away
- 10320-1/2 Blue Bluff RdMar 11, 2025Braker lane extension · 572 m away
- 10317-1/2 Blue Bluff RdMar 27, 2026Wildhorse pod b, section 1, phase 1b · 590 m away
- 10315-1/2 Blue Bluff RdNov 18, 2026Friesian boulevard extension · 593 m away
More offices in 78653.