Maypearl, TX 76064 · Maypearl ISD Paving Additions, High School And Middle School Additions

Maypearl ISD school additions and campus paving

TDLR registrations describe additions to Maypearl High School and Middle School, along with pavement replacement and new pavement in areas across the campus at 600 Phillips St. The additions were registered on February 2, 2024, and the paving project on April 9, 2024; both records show inspection complete.

Summarized from Texas Department of Licensing and Regulation records · updated Apr 9, 2024

Projects
2
2 filings
Latest filing
Apr 9, 2024
since Feb 2, 2024
Largest scope
199,300 sf
Estimated cost
$27M
state registration

Where this project stands

Inspected · closing out

Maypearl ISD Paving Additions

199,300 sq ft · $1.8M est.

  1. RegisteredApr 9, 2024
  2. Plan review
  3. ConstructionApr '24 – Apr '25
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 3 phone numbers

Permit & project history

2 projects
  1. Pavement removal and replacement and new pavement in specific areas throughout the school campus. 199,300 s.f. of pavement area total. — maypearl isd school campus

    TDLR project registrationRenovation/AlterationInspection Complete199,300 sq ft$1.8M est.
    Tenant / owner
    Maypearl ISD Paving Additions
    Design firm
    Pro
    Contact
    Pro
  2. Additions to an existing high school and middle school. — maypearl high school and middle school

    TDLR project registrationAdditions to Existing BuildingInspection Complete49,100 sq ft$27M est.
    Tenant / owner
    High School And Middle School Additions
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 600 Phillips St

What is being built at 600 Phillips St in Maypearl?

TDLR records describe additions to the existing high school and middle school, as well as campus paving work. Both project records show inspection complete.

Are new buildings being added to Maypearl High School and Middle School?

A TDLR registration dated February 2, 2024, describes additions to the existing high school and middle school. The record lists 49,100 square feet and shows inspection complete.

What paving work is planned at Maypearl ISD?

The Maypearl ISD Paving Additions registration describes pavement removal and replacement, plus new pavement in specific campus areas. It lists 199,300 square feet of pavement area and was filed April 9, 2024.

When were the Maypearl school projects registered?

The high school and middle school additions were registered on February 2, 2024. The campus paving project was registered on April 9, 2024.

How much is the Maypearl school additions project estimated to cost?

The TDLR registration for the high school and middle school additions lists an estimated cost of $27 million.

Are the Maypearl ISD projects complete?

Both TDLR project registrations list their status as inspection complete.