3000 Redbud Blvd
McKinney, TX 75069 · Ups Mckinney
UPS McKinney conveyor and parcel sortation installation
A conveyor and parcel sortation system is being installed inside the existing UPS McKinney facility at 3000 Redbud Blvd. The project was registered with TDLR on March 25, 2025, and its status is listed as review complete.
Summarized from Texas Department of Licensing and Regulation records · updated Mar 25, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Mar 25, 2025
- since Mar 25, 2025
- Largest scope
- 110,540 sf
- Estimated cost
- $7.0M
- state registration
Where this project stands
Finishing up · inspection nextUPS - McKinney, TX: Conveyor Install
110,540 sq ft · $7.0M est.
- RegisteredMar 25, 2025
- Plan review
- ConstructionApr '25 – Jul '25
- Inspectednow
- Closed
Scheduled to finish Jul 28, 2025; the state inspection hasn't been filed yet.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectInstallation of a material handling system to include the conveyor and parcel sortation equipment along with the respective support systems, interior to the existing facility. — ups mckinney
TDLR project registrationRenovation/AlterationReview Complete110,540 sq ft$7.0M est.- Project #
- TABS2025014980
- Tenant / owner
- Pro
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 3000 Redbud Blvd
What is being built at 3000 Redbud Blvd in McKinney?
A material handling system with conveyor and parcel sortation equipment is being installed inside the existing UPS McKinney facility. The TDLR registration describes the work as a renovation or alteration.
What is going in at UPS McKinney?
The project includes conveyor and parcel sortation equipment, along with supporting systems. The work is interior to the existing facility.
When was the UPS McKinney project filed?
The TDLR project registration, TABS2025014980, was filed on March 25, 2025. Its status is listed as review complete.
How large is the UPS McKinney project?
The TDLR record lists 110,540 square feet for the project.
How much is the UPS McKinney project estimated to cost?
The applicant's TDLR estimate for the project is $6,961,262.
What is being built near the City of McKinney on Redbud Boulevard?
At 3000 Redbud Blvd, the TDLR record describes an interior installation of conveyor and parcel sortation equipment at the existing UPS McKinney facility. The City of McKinney is listed at 3616 Redbud Blvd, about 17 meters away.
Also being built nearby
All of 75069- 3616 Redbud Blvd · City Of MckinneyJul 16, 2026Mckinney redbud storage and maintenance facility — new construction — new single-story storage and maintenance facility, approximately 9,352 sq ft with mezzanine. cmu wall construction with structural steel roof structure. includes associated site work, utilities, and accessible improvements. new construction · 17 m away
- 3490 Redbud Blvd · Paccar INCAug 28, 2026Dynacraft phase 1 mezzanine ti — renovation/alteration — interior renovation enclosing an existing open mezzanine area · 94 m away
- 1750 Wilmeth Rd · Qt South, LLCOct 16, 2025Quiktrip # 963 fryer project — renovation/alteration — includes re-organization of existing kichen equipment and addition of new fryer units. project 300 sq ft · 318 m away
- 1702 Wilmeth Rd · Classic CollisionApr 16, 2026Classic collision - mckinney — new construction — construction and site improvements for a 13,000 sq ft automotive collision repair facility · 331 m away
- 3250 S. Central Expressway · Alto Craig Crossing, LPApr 14, 2026Craig crossing shell building — new construction — new 7,748 sq ft shell building for future retail and/or restaurant use with associated site work · 346 m away
- 3210 N Central Expy · Rockefeller GroupNov 11, 2024Mckinney commerce center - building c — new construction — new industrial shell building & spec office · 354 m away
- 3200 N. Central Expy · Rg Mckinney Commerce Center Owner LLCJan 19, 202625095 - elliot electric ti — new construction — new open office area with private offices, conference room, restrooms and storage · 356 m away
- 3200 N. Central Expy · Rg Mckinney Commerce Center Owner LLCAug 3, 202625042 - mckinney commerce spec office - building a spec office — new construction — new construction of a 4776 sq ft office · 356 m away
- 3350 North Central Expy US 75 · Tractor Supply CoNov 8, 2024Tsc mckinney combo — additions to existing building — exterior greenhouse & feed center addition and an interior renovation. also, a 5,750 sq ft increase to the overall size of the impervious side yard is proposed · 359 m away
- 3350 S Central Expy · Lpl Real Estate Holdings LLCMay 13, 2025Pat lobb toyota — additions to existing building — addition of offices · 359 m away
- 3190 South Central Expressway · Alto Craig Crossing LPApr 4, 2024Petland mckinney — renovation/alteration — renovation of existing building for all architectural, mechanical, electrical, plumbing work as shown on drawing · 360 m away
- 3190 N. Central Expressway · Alto Craig Crossing LPJan 7, 2026Playtopia — renovation/alteration — new lease space in an existing retail center · 360 m away