McKinney Soccer Complex Phase 2 plans turf and site upgrades

Phase 2 at McKinney Soccer Complex includes converting grass soccer fields to synthetic turf and adding hardscape improvements, a playground, misting elements, shade structures, a plaza, seatwalls, landscaping and irrigation. The project was registered with the Texas Department of Licensing and Regulation on July 11, 2024. The applicant’s estimated project cost is $28 million.

Summarized from Texas Department of Licensing and Regulation records · updated Jul 11, 2024

Projects
1
1 filings
Latest filing
Jul 11, 2024
since Jul 11, 2024
Largest scope
1,219,680 sf
Estimated cost
$28M
state registration

Where this project stands

Under construction

McKinney Soccer Complex Phase 2

1,219,680 sq ft · $28M est.

  1. RegisteredJul 11, 2024
  2. Plan review
  3. ConstructionSep '24 – Feb '27
  4. Inspected
  5. Closed
92% through of a 29-month buildSep 1, 2024 → Feb 1, 2027

4 contacts on this project · 2 phone numbers

Permit & project history

1 project
  1. Converting grass soccer fields to synthetic turf, hardscape improvements, playground, misting elements, shade structures plaza construction, seatwalls, landscaping and irrigation. — mckinney soccer complex

    TDLR project registrationRenovation/AlterationReview Complete1,219,680 sq ft$28M est.
    Tenant / owner
    Mckinney Soccer Complex Phase 2
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 6375 Collin Mckinney Parkway

What is being built at 6375 Collin Mckinney Parkway?

The McKinney Soccer Complex Phase 2 project plans to replace grass soccer fields with synthetic turf and make other site improvements. The registration also lists a playground, misting elements, shade structures, a plaza, seatwalls, landscaping and irrigation.

When was McKinney Soccer Complex Phase 2 registered?

The project was registered with the Texas Department of Licensing and Regulation on July 11, 2024. Its registration number is TABS2024022823.

Is McKinney Soccer Complex getting synthetic turf?

Yes. The Phase 2 project description says grass soccer fields will be converted to synthetic turf.

What improvements are planned at McKinney Soccer Complex?

The project description includes hardscape improvements, a playground, misting elements, shade structures, plaza construction, seatwalls, landscaping and irrigation, along with synthetic turf.

How much is the McKinney Soccer Complex Phase 2 project estimated to cost?

The TDLR registration lists an applicant-estimated cost of $28 million for the project.