9890 FM 2757
Mesquite, TX 75126 · City Of Mesquite
Mesquite Fire Station No. 8 registered at 9890 FM 2757
A single-story fire station with a four-bay apparatus garage, living space and police substation is planned at 9890 FM 2757. Its TDLR project registration was filed November 13, 2024, and the record lists the project as inspection complete. The applicant estimated the project cost at $11.7 million.
Summarized from Texas Department of Licensing and Regulation records · updated Nov 13, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Nov 13, 2024
- since Nov 13, 2024
- Largest scope
- 17,180 sf
- Estimated cost
- $12M
- state registration
Where this project stands
Inspected · closing outMesquite Fire Station No.8
17,180 sq ft · $12M est.
- RegisteredNov 13, 2024
- Plan review
- ConstructionNov '24 – Mar '26
- Inspected
- Closednow
The building is substantially done. Move-in, fit-out and service work usually follow.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectSingle story, sprinklered, 17,179 square foot fire station consisting of a four bay apparatus garage, fire station living space, and police substation. — mesquite fire station no.8
TDLR project registrationNew ConstructionInspection Complete17,180 sq ft$12M est.- Project #
- TABS2025005458
- Tenant / owner
- Mesquite Fire Station No.8
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 9890 FM 2757
What is being built at 9890 FM 2757 in Mesquite?
The project is Mesquite Fire Station No. 8, a single-story fire station that includes a four-bay apparatus garage, fire station living space and a police substation. The TDLR registration was filed November 13, 2024.
How large is Mesquite Fire Station No. 8?
The TDLR record lists the project at 17,179 square feet.
What is the estimated cost of the fire station at 9890 FM 2757?
The applicant's TDLR estimate is $11.7 million. This is an estimate for the project, not a reported final cost.
Is the Mesquite Fire Station No. 8 project complete?
The TDLR project record lists its status as inspection complete. It does not provide a completion date.
What's being built near Ch Tnc Mesquite Owner on FM 2757?
Mesquite Fire Station No. 8 is registered at 9890 FM 2757, about 72 meters from the nearby listing at 9850 FM 2757.