groundranger
Recent · latest filing Feb 2026Commercial

8830 Co. Rd

Miami, TX 79059 · Ip Meitner Land LLC

Data center building planned near Miami

A 761,000-square-foot, one-story data center building with associated central utility buildings is planned at 8830 Co. Rd near Miami. Project Pumpkin 2A was registered with the Texas Department of Licensing and Regulation on February 8, 2026.

Summarized from Texas Department of Licensing and Regulation records · updated Feb 8, 2026

Projects
1
1 filings
Latest filing
Feb 8, 2026
since Feb 8, 2026
Largest scope
761,000 sf
Estimated cost
$400M
state registration

Where this project stands

In state plan review

Project Pumpkin 2A

761,000 sq ft · $400M est.

  1. RegisteredFeb 8, 2026
  2. Plan reviewnow
  3. ConstructionFeb '26 – Dec '27
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Project Pumpkin 2A

    1-story data center with associated central utility buildings. — data center building 2a

    TDLR project registrationNew ConstructionProject Registered761,000 sq ft$400M est.
    Tenant / owner
    Project Pumpkin 2a
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 8830 Co. Rd

What is being built at 8830 Co. Rd near Miami, TX?

A one-story data center building with associated central utility buildings is planned. The TDLR registration describes it as data center building 2A.

How large is the Project Pumpkin 2A data center?

The registered project is listed at 761,000 square feet.

When was the data center project registered?

Project Pumpkin 2A was registered with the Texas Department of Licensing and Regulation on February 8, 2026.

What is the estimated cost of Project Pumpkin 2A?

The TDLR registration lists an estimated project cost of $400 million. This is an applicant estimate, not a reported total project cost.

Is Project Pumpkin 2A a data center?

Yes. The TDLR registration describes a one-story data center building with associated central utility buildings.

Email me when plan review is complete