groundranger
Recent · latest filing Apr 2026Commercial

881 Miller Road

Midlothian, TX 76065 · Prairie Ridge Phase 1 Owner LP

224,152-square-foot data center registered in Midlothian

A two-story, 224,152-square-foot single-tenant computer data center core and shell is planned at 881 Miller Road in Midlothian. The Texas Department of Licensing and Regulation registered the project on April 2, 2026. The applicant’s estimated project cost is $72,590,278.

Summarized from Texas Department of Licensing and Regulation records · updated Apr 2, 2026

Projects
1
1 filings
Latest filing
Apr 2, 2026
since Apr 2, 2026
Largest scope
224,152 sf
Estimated cost
$73M
state registration

Where this project stands

In state plan review

AREP Power House Grand Prairie

224,152 sq ft · $73M est.

  1. RegisteredApr 2, 2026
  2. Plan reviewnow
  3. ConstructionApr '26 – Apr '28
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. 224,152 sq ft two story single tenant computer data center core and shell build out. — data center building 1

    TDLR project registrationNew ConstructionProject Registered224,152 sq ft$73M est.
    Tenant / owner
    Arep Power House Grand Prairie
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 881 Miller Road

What is being built at 881 Miller Road in Midlothian?

A two-story, 224,152-square-foot single-tenant computer data center core and shell is listed in TDLR project registration TABS2026016734, filed April 2, 2026.

Is a data center planned for 881 Miller Road?

Yes. The TDLR registration describes a computer data center building 1, with a listed area of 224,152 square feet.

Who is the project for at 881 Miller Road?

The registration names the project AREP Power House Grand Prairie. It describes the building as a single-tenant computer data center.

When was the 881 Miller Road data center registered?

The project was registered with the Texas Department of Licensing and Regulation on April 2, 2026.

How much is the planned data center at 881 Miller Road estimated to cost?

The applicant’s estimated cost for the project is $72,590,278, according to TDLR registration TABS2026016734.