21548 FM 471 S
Natalia, TX 78059 · Love's Travel Stops & Country Stores Inc.
Love's EV charging station registered in Natalia
A Love's site at 21548 FM 471 S is planned for two dual electric vehicle charging stations, four powerblock modules and 2,000-amp electrical switchgear. The TDLR project registration was filed March 25, 2025, and lists a 1,600-square-foot renovation. The applicant's estimated project cost is $600,000.
Summarized from Texas Department of Licensing and Regulation records · updated Mar 25, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Mar 25, 2025
- since Mar 25, 2025
- Largest scope
- 1,600 sf
- Estimated cost
- $600K
- state registration
Where this project stands
CompletedLove's 471 EV Charging Station
1,600 sq ft · $600K est.
- RegisteredMar 25, 2025
- Plan review
- ConstructionMay '25 – Aug '25
- Inspected
- Closed
Ran as a 3-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectInstallaiton of two dual electric vehicle charging stations, four powerblock modules, one 2000a electrical switchgear. — loves travel stops & country stores
TDLR project registrationRenovation/AlterationProject Closed1,600 sq ft$600K est.- Project #
- TABS2025015012
- Tenant / owner
- Love's 471 Ev Charging Station
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 21548 FM 471 S
What is being built at 21548 FM 471 S in Natalia?
A TDLR registration describes installation of two dual electric vehicle charging stations, four powerblock modules and 2,000-amp electrical switchgear at the Love's site.
Is Love's adding EV chargers in Natalia?
The March 25, 2025, TDLR registration for Love's 471 EV Charging Station describes installing two dual electric vehicle charging stations.
How many EV charging stations are planned at the Love's in Natalia?
The project registration lists two dual electric vehicle charging stations.
What equipment is included in the Love's EV charging project?
The registration lists two dual electric vehicle charging stations, four powerblock modules and 2,000-amp electrical switchgear.
When was the Love's charging station project filed?
The TDLR project registration, TABS2025015012, was filed March 25, 2025.
How much will the Love's EV charging project cost?
The applicant's estimated cost for the project is $600,000. This is an estimate, not a reported final cost.
Is the Love's EV charging project complete?
The TDLR record lists the project status as “Project Closed.” The record describes the planned installation but does not confirm when the work was completed.