2300 N. Twin Hwy
Nederland, TX 77627 · Energy Transfer
Energy Transfer control building registered in Nederland
A 4,000-square-foot standalone control building with offices and a break room is planned at 2300 N. Twin Hwy in Nederland. A TDLR project registration was filed on July 17, 2024, and lists the project status as Inspection Complete. The applicant’s estimated project cost is $1.4 million.
Summarized from Texas Department of Licensing and Regulation records · updated Jul 17, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Jul 17, 2024
- since Jul 17, 2024
- Largest scope
- 4,000 sf
- Estimated cost
- $1.4M
- state registration
Where this project stands
Inspected · closing outEnergy Transfer Control Building
4,000 sq ft · $1.4M est.
- RegisteredJul 17, 2024
- Plan review
- ConstructionAug '24 – Aug '25
- Inspected
- Closednow
The building is substantially done. Move-in, fit-out and service work usually follow.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectStand alone control building with offices and break room. — energy transfer control
TDLR project registrationNew ConstructionInspection Complete4,000 sq ft$1.4M est.- Project #
- TABS2024023231
- Tenant / owner
- Energy Transfer Control Building
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 2300 N. Twin Hwy
What is being built at 2300 N. Twin Hwy in Nederland?
A TDLR registration describes a standalone control building with offices and a break room. The project is named Energy Transfer Control Building.
Who is the control building for?
The project is named Energy Transfer Control Building, and the fact sheet lists Energy Transfer as the occupant or owner.
How large is the Energy Transfer control building?
The TDLR registration lists the building at 4,000 square feet.
When was the project registered?
The TDLR project registration, TABS2024023231, was filed on July 17, 2024.
What is the estimated cost of the Nederland control building?
The applicant’s estimated cost for the project is $1.4 million.
Is the Energy Transfer control building complete?
The TDLR registration lists the project status as Inspection Complete.