Historic · latest filing Mar 2025Commercial

215 Rebecca Creek Rd

New Braunfels, TX 78239 · Comal County Esd No 4

A 2,770-square-foot garage addition for Comal ESD No. 4

A new garage addition for the Comal ESD No. 4 fire station was registered on March 11, 2025, at 215 Rebecca Creek Rd. The TDLR record lists 2,770 square feet, an applicant-estimated project cost of $800,000, and a status of inspection complete.

Summarized from Texas Department of Licensing and Regulation records · updated Mar 11, 2025

Projects
1
1 filings
Latest filing
Mar 11, 2025
since Mar 11, 2025
Largest scope
2,770 sf
Estimated cost
$800K
state registration

Where this project stands

Inspected · closing out

Comal ESD No. 4 Fire Station Structure Addition

2,770 sq ft · $800K est.

  1. RegisteredMar 11, 2025
  2. Plan review
  3. ConstructionMay '25 – Sep '25
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 2 phone numbers

Permit & project history

1 project
  1. New garage — comal esd no. 4 fire station

    TDLR project registrationNew ConstructionInspection Complete2,770 sq ft$800K est.
    Tenant / owner
    Comal Esd No. 4 Fire Station Structure Addition
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 215 Rebecca Creek Rd

What is being built at 215 Rebecca Creek Rd?

A new garage addition for the Comal ESD No. 4 fire station was registered at this address. The TDLR project record lists 2,770 square feet.

When was the Comal ESD No. 4 garage project filed?

The TDLR registration for Comal ESD No. 4 Fire Station Structure Addition is dated March 11, 2025. Its project number is TABS2025013941.

How large is the new Comal ESD No. 4 garage?

The TDLR record lists the garage addition at 2,770 square feet.

How much will the fire station garage addition cost?

The TDLR registration lists an applicant-estimated cost of $800,000 for the project. This is an estimate, not a confirmed final cost.

Is the Comal ESD No. 4 garage project complete?

The TDLR record lists the project status as inspection complete.

What is being built near Comal Independent School District on FM 311?

A new garage addition for the Comal ESD No. 4 fire station is registered at 215 Rebecca Creek Rd, about 404 meters from Comal Independent School District at 6101 FM 311.

Also being built nearby

All of 78239
Email me when the project is closed