Alvin ISD security vestibules slated for renovation
Alvin ISD registered a renovation project for existing security vestibules at three campuses, including Brothers Elementary at 2910 Halfmoon Bay Drive in Pearland. The TDLR project registration is dated December 24, 2024, and lists an estimated project cost of $1 million.
Summarized from Texas Department of Licensing and Regulation records · updated Dec 24, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Dec 24, 2024
- since Dec 24, 2024
- Largest scope
- 8,000 sf
- Estimated cost
- $1.0M
- state registration
Where this project stands
Inspected · closing outAlvin ISD Phase 1-B Security Vestibule Upgrades
8,000 sq ft · $1.0M est.
- RegisteredDec 24, 2024
- Plan review
- ConstructionMay '25 – Dec '25
- Inspected
- Closednow
The building is substantially done. Move-in, fit-out and service work usually follow.
4 contacts on this project · 2 phone numbers
Permit & project history
1 projectRenovation to existing security vestibules for 3 campuses brothers elem. school - 2910 halfmoon bay dr. pearland tx. 77584 sanchez elem. school -1721 sterling lakes dr. west, rosharon, tx 77583 alvin jr. high school 2300 w south st, alvin, tx 77511 — shirley dill brothers elementary school
TDLR project registrationRenovation/AlterationInspection Complete8,000 sq ft$1.0M est.- Project #
- TABS2025008451
- Tenant / owner
- Alvin ISD Phase 1-B Security Vestibule Upgrades
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 2910 Halfmoon
What is being built at 2910 Halfmoon Bay Drive in Pearland?
The project calls for renovations to existing security vestibules at Brothers Elementary and two other Alvin ISD campuses. It is not listed as new construction.
What is the Alvin ISD project at 2910 Halfmoon?
Alvin ISD’s Phase 1-B Security Vestibule Upgrades project includes work at Brothers Elementary, Sanchez Elementary and Alvin Junior High. The TDLR registration is TABS2025008451.
When was the security vestibule project registered?
The TDLR project registration is dated December 24, 2024.
How much will the Alvin ISD vestibule renovations cost?
The TDLR record lists an estimated project cost of $1 million. This is the applicant’s estimate for the project.
How many campuses are included in the project?
The registration describes renovations to existing security vestibules at three campuses: Brothers Elementary, Sanchez Elementary and Alvin Junior High.
Is the security vestibule project complete?
The TDLR record lists the project status as “Inspection Complete.”