Memorial High School field conversion to synthetic turf
A project at Memorial High School would convert an existing grass athletics field to synthetic turf. The Texas Department of Licensing and Regulation registration was filed February 9, 2026, under project number TABS2026012033. The applicant's estimated project cost is $2.6 million.
Summarized from Texas Department of Licensing and Regulation records · updated Feb 9, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Feb 9, 2026
- since Feb 9, 2026
- Largest scope
- 186,000 sf
- Estimated cost
- $2.6M
- state registration
Where this project stands
CompletedMemorial HS Baseball & Softball Improvements
186,000 sq ft · $2.6M est.
- RegisteredFeb 9, 2026
- Plan review
- ConstructionSep '25 – Feb '26
- Inspected
- Closed
Ran as a 5-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectExisting grass field to be converted to synthetic turf field — memorial high school - athletics
TDLR project registrationRenovation/AlterationProject Closed186,000 sq ft$2.6M est.- Project #
- TABS2026012033
- Tenant / owner
- Memorial Hs Baseball & Softball Improvements
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 3501 Lucian Adams St
What is being built at 3501 Lucian Adams St?
A TDLR project registration describes converting an existing grass field at Memorial High School to synthetic turf for athletics. The registration was filed February 9, 2026, as project TABS2026012033.
Is Memorial High School getting a synthetic turf field?
The registration describes converting an existing grass field to synthetic turf. It does not specify a construction schedule.
When was the Memorial High School field project filed?
The TDLR registration was filed February 9, 2026. Its project number is TABS2026012033.
How much will the Memorial High School turf project cost?
The applicant's estimated cost is $2.6 million. This is the estimate in the TDLR registration, not a confirmed final cost.
Is the Memorial High School field project complete?
The TDLR record lists the project status as closed, but that status alone does not confirm that construction is complete.