2600 Rufford
Richardson, TX 75080 · The University Of Texas Dallas – Science Building
UT Dallas Science Building lab wing finish-out
A 18,965-square-foot interior finish-out for a lab wing is planned on Level 4 of the existing UT Dallas Science Building at 2600 Rufford. The project was registered with TDLR on July 2, 2025; the registration describes no exterior or restroom work. The applicant estimated the project cost at $5.4 million.
Summarized from Texas Department of Licensing and Regulation records · updated Jul 2, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Jul 2, 2025
- since Jul 2, 2025
- Largest scope
- 18,965 sf
- Estimated cost
- $5.4M
- state registration
Where this project stands
CompletedScience building Level 4 Finish Out – Lab Wing
18,965 sq ft · $5.4M est.
- RegisteredJul 2, 2025
- Plan review
- ConstructionJul '25 – Feb '26
- Inspected
- Closed
Ran as a 8-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectInterior finish out an existing building. no exterior scope. no restroom scope — the university of texas dallas – science building
TDLR project registrationRenovation/AlterationProject Closed18,965 sq ft$5.4M est.- Project #
- TABS2025022668
- Tenant / owner
- Science Building Level 4 Finish Out – Lab Wing
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 2600 Rufford
What is being built at 2600 Rufford in Richardson?
A lab wing is being finished out on Level 4 of the existing UT Dallas Science Building. The TDLR registration describes interior work only, with no exterior or restroom scope.
Is UT Dallas building a new science building in Richardson?
The registration describes a finish-out inside an existing science building, not construction of a new building. It was filed with TDLR on July 2, 2025.
How large is the UT Dallas lab wing project?
The TDLR registration lists the project at 18,965 square feet.
How much will the UT Dallas Science Building renovation cost?
The applicant's TDLR registration estimates the project cost at $5.4 million. This is an estimate for the project, not a confirmed final cost.
When was the UT Dallas Science Building lab project filed?
The project was registered on July 2, 2025. Its TDLR project number is TABS2025022668.
Is the UT Dallas lab wing project complete?
The TDLR record lists the project status as closed. The record describes a planned interior finish-out but does not state when construction was completed.