200 Dell Way
Round Rock, TX 78664 · Dell Round Rock Power Lab, Rr5-2 Acculogic Equipment Install + 6 more
Server and lab equipment upgrades registered at 200 Dell Way
TDLR registrations describe equipment and building-system upgrades in a multi-tenant building at 200 Dell Way, including server equipment, testing equipment, and mechanical and electrical work. The latest project was registered on October 21, 2026; another equipment installation was registered on September 11, 2026.
Summarized from Texas Department of Licensing and Regulation records · updated Oct 21, 2026
- Projects
- 8
- 8 filings
- Latest filing
- Oct 21, 2026
- since Mar 12, 2024
- Largest scope
- 13,378 sf
- Estimated cost
- $8.0M
- state registration
Where this project stands
In state plan reviewDell Round Rock Power Lab
1,993 sq ft · $4.0M est.
- RegisteredOct 21, 2026
- Plan reviewnow
- ConstructionNov '26 – Apr '27
- Inspected
- Closed
Construction is scheduled to start Nov 23, 2026. Subcontractors and suppliers are usually picked in the weeks before.
4 contacts on this project · 3 phone numbers
Permit & project history
8 projectsInstallation of new server equipment with limited exterior work for installation of new mechanical and electrical equipment. interior work includes reusing of existing raised access flooring and ceilings, construction of a new cage partition. — rr5
TDLR project registrationRenovation/AlterationProject Registered1,993 sq ft$4.0M est.- Project #
- TABS2027004115
- Tenant / owner
- Dell Round Rock Power Lab
- Design firm
- Pro
- Contact
- Pro
Installation of new testing equipment in an existing building. exterior work includes the temporary removal of an existing curtain wall system to crane the new equipment onto the second floor. — rr5
TDLR project registrationRenovation/AlterationProject Registered735 sq ft$50K est.- Project #
- TABS2027000817
- Tenant / owner
- Rr5-2 Acculogic Equipment Install
- Design firm
- Pro
- Contact
- Pro
Installation of new server equipment, includes limited exterior work for installation of new mechanical and electrical equipment. construction of new partitions, flooring, ceiling, finishes and mep systems. — building 5
TDLR project registrationRenovation/AlterationInspection Complete13,378 sq ft$8.0M est.- Project #
- TABS2026003611
- Tenant / owner
- Dell Round Rock Flex Lab Phase 2
- Design firm
- Pro
- Contact
- Pro
Modification to the layout of existing equipment and associated storage areas, installation of new mechanical and electrical equipment and infrastructure, and installation of new owner provided server equipment. — building 5
TDLR project registrationRenovation/AlterationInspection Complete2,500 sq ft$1.0M est.- Project #
- TABS2025025868
- Tenant / owner
- Dell Round Rock 5 Comms Lab
- Design firm
- Pro
- Contact
- Pro
Mep systems upgrade and expansion, installation of new server racks, new exterior mep equipment yard, minor modifications of existing finishes. exterior scope includes ne concrete pads and security fencing. — rr5
TDLR project registrationRenovation/AlterationReview Complete930 sq ft$1.0M est.- Project #
- TABS2025023757
- Tenant / owner
- Dell Round Rock 5 Thermal Lab
- Design firm
- Pro
- Contact
- Pro
Installation of new equipment and minor revision to interior partitions and raised access floor systems. — rr5
TDLR project registrationRenovation/AlterationReview Complete1,680 sq ft$250K est.- Project #
- TABS2025017014
- Tenant / owner
- Rr5-1 Splash Lab
- Design firm
- Pro
- Contact
- Pro
Replacement of reception desk and related casework, new data and power drops. — rr5
TDLR project registrationRenovation/AlterationReview Complete266 sq ft$115K est.- Project #
- TABS2024013620
- Tenant / owner
- Lobby Desk Update - Rr5
- Design firm
- Pro
- Contact
- Pro
Interior remodel of existing space for additional server racks with mep infrastructure added. — 5
TDLR project registrationRenovation/AlterationProject Closed35,399 sq ft$3.9M est.- Project #
- TABS2023022634
- Tenant / owner
- Dell Rr5-2 Flex Lab
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 200 Dell Way
What is being built at 200 Dell Way?
TDLR records describe renovations and equipment installations in an existing multi-tenant building, including server equipment, testing equipment, and mechanical and electrical upgrades. The latest registration, for Dell Round Rock Power Lab, was filed October 21, 2026.
Is a new building going up at 200 Dell Way?
The records describe work inside existing buildings, including equipment installation and interior changes. They do not describe a new standalone building.
What is the Dell Round Rock Power Lab project?
The October 21, 2026 TDLR registration describes installing server equipment and mechanical and electrical equipment, along with a new cage partition. The work is listed as a renovation or alteration.
What is the Acculogic project at 200 Dell Way?
A TDLR registration filed September 11, 2026, describes installing testing equipment in an existing building. The work includes temporarily removing part of the curtain wall to bring equipment to the second floor.
When were the latest projects at 200 Dell Way registered?
The latest registration was filed October 21, 2026, for Dell Round Rock Power Lab. Another registration for the RR5-2 Acculogic Equipment Install was filed September 11, 2026.
What's being worked on near QuikTrip #4138 on Mays Street?
At 200 Dell Way, about 390 meters from the QuikTrip #4138 Fryer Project, TDLR records describe server and testing equipment installations and related building upgrades. The latest project registration there was filed October 21, 2026.
Also being built nearby
All of 78664- 2231 S, Mays St · Qt South, LLCDec 10, 2025Quiktrip #4138 fryer project — renovation/alteration — includes reorganization of existing kitchen equipment and addition of new fryer units. 300sf · 390 m away
- 401 Dell WayAug 27, 2025Dell rr1 studio expansion — renovation/alteration — interior renovation of studio and offices to expand studio including finishes, mechanical, and electrical · 412 m away
- 401 Dell Way Rr1, SecondMar 11, 2024Rr1 boardroom video wall — renovation/alteration — replacement of existing a/v equipment and finish materials. limited modifications to mechanical, electrical, and low voltage system required for installation of new a/v equipment · 412 m away
- 115 Sundance Pkwy · Dlc Management CorpSep 19, 2025Rush bowls — renovation/alteration — renovation to install restaurant venue · 555 m away