635 Rayburn Drive
San Antonio, TX 78221 · Rayburn Legacy Park Gym
Rayburn Legacy Park Gym renovation registered in February 2025
A renovation at Rayburn Legacy Park Gym, listed in connection with the 2025 NCAA Men's Final Four, was registered with the Texas Department of Licensing and Regulation on February 6, 2025. The 48,783-square-foot project includes a new concrete entrance and ornamental gate, trail improvements, and interior updates; the applicant estimated its cost at $150,000.
Summarized from Texas Department of Licensing and Regulation records · updated Feb 6, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Feb 6, 2025
- since Feb 6, 2025
- Largest scope
- 48,783 sf
- Estimated cost
- $150K
- state registration
Where this project stands
Completed2025 NCAA Men's Final Four - Rayburn Legacy Park at Harlendale ISD
48,783 sq ft · $150K est.
- RegisteredFeb 6, 2025
- Plan review
- ConstructionFeb '25 – Apr '25
- Inspected
- Closed
Ran as a 2-month build.
4 contacts on this project · 4 phone numbers
Permit & project history
1 projectExterior will include concrete entrance with ornamental gate, & improvements to existing walking trail. interior include new hvac, replacing toilet fixtures, insulation, lighting and painting. — rayburn legacy park gym
TDLR project registrationRenovation/AlterationProject Closed48,783 sq ft$150K est.- Project #
- TABS2025011199
- Tenant / owner
- 2025 Ncaa Men's Final Four - Rayburn Legacy Park At Harlendale ISD
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 635 Rayburn Drive
What is being built at 635 Rayburn Drive?
The project is a renovation of Rayburn Legacy Park Gym, not a listed new building. Plans include an entrance and ornamental gate, improvements to an existing walking trail, and interior updates.
When was the Rayburn Legacy Park Gym project filed?
The Texas Department of Licensing and Regulation project registration was filed on February 6, 2025. Its record lists the project as closed.
What renovations are planned for Rayburn Legacy Park Gym?
The registration describes a concrete entrance with an ornamental gate, improvements to the existing walking trail, new HVAC, replacement toilet fixtures, insulation, lighting, and painting.
How much will the Rayburn Legacy Park Gym renovation cost?
The applicant's estimated project cost is $150,000. This is an estimate, not a confirmed final cost.
Is Rayburn Legacy Park Gym being renovated for the 2025 NCAA Men's Final Four?
The project is named “2025 NCAA Men's Final Four - Rayburn Legacy Park at Harlendale ISD.” Its registration describes renovation work at the gym.
What is being built near CCP Dark 7-11 on Southwest Military Drive?
About 381 meters from CCP Dark 7-11, Rayburn Legacy Park Gym has a registered renovation project. Plans include exterior entrance and trail work as well as interior updates.
What construction is planned near the 1102 SW Military Drive shell building?
Rayburn Legacy Park Gym, about 550 meters away, has a renovation registration dated February 6, 2025. The work includes upgrades to the gym and its existing walking trail.