San Antonio, TX 78228 · Northside Independent School District

New athletic facility and upgrades planned at Sul Ross Middle School

A new athletic facility is planned at Sul Ross Middle School, along with bus and fire lane improvements, lighting and energy controls upgrades, security work, and renovations for fine arts classrooms. The project was registered with TDLR on August 15, 2024; the applicant estimated its cost at $15.675 million.

Summarized from Texas Department of Licensing and Regulation records · updated Aug 15, 2024

Projects
1
1 filings
Latest filing
Aug 15, 2024
since Aug 15, 2024
Largest scope
29,589 sf
Estimated cost
$16M
state registration

Where this project stands

Inspected · closing out

Athletics, Lighting & Controls Upgrades At Ross Middle School

29,589 sq ft · $16M est.

  1. RegisteredAug 15, 2024
  2. Plan review
  3. ConstructionNov '24 – Jan '26
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Demolition of existing buildings for a new athletic facility, bus and fire lane improvements, lighting & energy controls upgrades, security vestibule/fencing/fenestration upgrades, and renovation of existing areas for new fine arts classrooms. — sul ross middle school

    TDLR project registrationNew ConstructionInspection Complete29,589 sq ft$16M est.
    Tenant / owner
    Athletics, Lighting & Controls Upgrades At Ross Middle School
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 3630 Callaghan Road

What is being built at 3630 Callaghan Road?

A new athletic facility is planned at Sul Ross Middle School, along with site improvements and renovations to existing areas for fine arts classrooms. The TDLR registration describes 29,589 square feet of work.

What upgrades are planned at Sul Ross Middle School?

The project includes lighting and energy controls upgrades, security vestibule, fencing and fenestration upgrades, and bus and fire lane improvements. Existing areas are also slated for renovation into fine arts classrooms.

When was the Sul Ross Middle School project permitted?

The project was registered with the Texas Department of Licensing and Regulation on August 15, 2024. Its registration number is TABS2024025547.

How much will the Sul Ross Middle School project cost?

The applicant's TDLR registration estimated the project cost at $15.675 million. This is an estimate for the project, not a final reported cost.

What's being built near San Antonio Karen Baptist Church on Callaghan Road?

About 197 meters from the church, the Sul Ross Middle School project includes a new athletic facility and improvements to school buildings and site features. The project was registered on August 15, 2024.

What school construction is happening near Northside ISD on Hemphill Drive?

The project at Sul Ross Middle School, about 377 meters from the Northside ISD address on Hemphill Drive, includes a new athletic facility and other campus upgrades. TDLR lists the project as 29,589 square feet.

Also being built nearby

All of 78228

More demolitions in 78228, gyms & fitness in 78228, schools & daycares in 78228.

Email me when the project is closed