9390 SW Loop

San Antonio, TX 78242 · Swisd Fencing Project - Medio Creek Elementary, Swisd Fencing Project - Mcauliffe Middle School

SWISD fencing and gate replacements registered at 9390 SW Loop

Two fencing projects are registered at this multi-tenant commercial site: work at Medio Creek Elementary and McAuliffe Middle School. TDLR registrations dated February 6, 2025, describe demolishing and replacing existing fences and gates to secure each campus.

Summarized from Texas Department of Licensing and Regulation records · updated Feb 6, 2025

Projects
2
2 filings
Latest filing
Feb 6, 2025
since Feb 6, 2025
Largest scope
200 sf
Estimated cost
$576K
state registration

Where this project stands

Inspected · closing out

SWISD FENCING PROJECT - MEDIO CREEK ELEMENTARY

200 sq ft · $367K est.

  1. RegisteredFeb 6, 2025
  2. Plan review
  3. ConstructionApr '25 – Dec '25
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 2 phone numbers

Permit & project history

2 projects
  1. Demolish and replace existing fencing/gates and install new fencing/gates to secure campus. — medio creek elementary

    TDLR project registrationRenovation/AlterationInspection Complete200 sq ft$367K est.
    Tenant / owner
    Swisd Fencing Project - Medio Creek Elementary
    Design firm
    Pro
    Contact
    Pro
  2. Demolish and replace existing fencing/gates and install new fencing/gates to secure campus. — mcauliffe middle school

    TDLR project registrationRenovation/AlterationInspection Complete200 sq ft$576K est.
    Tenant / owner
    Swisd Fencing Project - Mcauliffe Middle School
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 9390 SW Loop

What is being built at 9390 SW Loop?

TDLR records show fencing and gate replacement work for two SWISD schools: Medio Creek Elementary and McAuliffe Middle School. Both projects were registered on February 6, 2025.

Is a new building planned at 9390 SW Loop?

The records describe renovation work to demolish and replace existing fencing and gates, not construction of a new building.

What is the fencing project at Medio Creek Elementary?

The project registration calls for demolishing and replacing existing fencing and gates to secure the campus. It was registered February 6, 2025, as TABS2025011312.

What work is planned at McAuliffe Middle School?

The registration describes demolishing and replacing existing fencing and gates to secure the campus. The project, TABS2025011310, was registered February 6, 2025.

When were the SWISD fencing projects registered?

Both TDLR project registrations are dated February 6, 2025.

How much will the SWISD fencing work cost?

The fact sheet lists a TDLR estimated cost of $575,650. This is an estimate, not a confirmed final project cost.