groundranger
Historic · latest filing Nov 2024Commercial

875 North Hunt Lane

San Antonio, TX 78251 · Valvoline Instant Oil Change

Valvoline Instant Oil Change planned at 875 North Hunt Lane

A 3,763-square-foot Valvoline Instant Oil Change facility with a lube pit is planned at 875 North Hunt Lane. The Texas Department of Licensing and Regulation registered the new-construction project on November 5, 2024; its estimated cost is $1.449 million.

Summarized from Texas Department of Licensing and Regulation records · updated Nov 5, 2024

Projects
1
1 filings
Latest filing
Nov 5, 2024
since Nov 5, 2024
Largest scope
3,763 sf
Estimated cost
$1.4M
state registration

Where this project stands

Finishing up · inspection next

Valvoline Instant Oil Change

3,763 sq ft · $1.4M est.

  1. RegisteredNov 5, 2024
  2. Plan review
  3. ConstructionMar '25 – Sep '25
  4. Inspectednow
  5. Closed

Scheduled to finish Sep 30, 2025; the state inspection hasn't been filed yet.

4 contacts on this project · 2 phone numbers

Permit & project history

1 project
  1. New construction valvoline with lube pit — valvoline instant oil change

    TDLR project registrationNew ConstructionReview Complete3,763 sq ft$1.4M est.
    Tenant / owner
    Valvoline Instant Oil Change
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 875 North Hunt Lane

What is being built at 875 North Hunt Lane?

A new Valvoline Instant Oil Change facility with a lube pit is planned for the address. The TDLR registration lists 3,763 square feet.

Is a Valvoline Instant Oil Change coming to San Antonio 78251?

A TDLR project registration names Valvoline Instant Oil Change for 875 North Hunt Lane, San Antonio, TX 78251. The project was registered November 5, 2024.

How large will the Valvoline at 875 North Hunt Lane be?

The TDLR registration lists the new-construction project at 3,763 square feet.

What is the estimated cost of the Valvoline project?

The applicant's TDLR estimate is $1.449 million for the project.

What is the project number for the Valvoline on North Hunt Lane?

The TDLR project registration number is TABS2025004874. It was registered on November 5, 2024.

Email me when it passes inspection