AEP registers 11,110-square-foot substation building

A new 11,110-square-foot gas-insulated switch station building is planned for South Padre Substation No. 1057 at 28996 State Park Rd. AEP Texas Central Company registered the project with TDLR on September 10, 2025; the applicant's estimated project cost is $12.18 million.

Summarized from Texas Department of Licensing and Regulation records · updated Sep 10, 2025

Projects
1
1 filings
Latest filing
Sep 10, 2025
since Sep 10, 2025
Largest scope
11,110 sf
Estimated cost
$12M
state registration

Where this project stands

Finishing up · inspection next

New GIS Building for South Padre Substation No. 1057

11,110 sq ft · $12M est.

  1. RegisteredSep 10, 2025
  2. Plan review
  3. ConstructionSep '25 – Jun '26
  4. Inspectednow
  5. Closed

Scheduled to finish Jun 22, 2026; the state inspection hasn't been filed yet.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. The project generally consist of a new 11,110 sq ft gas insulated switch station (gis) building that will house gis switch gear, transformers, batteries, and associated controls. the building will be constructed of pre-cast concrete panels. — south padre substation no. 1057

    TDLR project registrationNew ConstructionReview Complete11,110 sq ft$12M est.
    Tenant / owner
    New Gis Building For South Padre Substation No. 1057
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 28996 State Park Rd

What is being built at 28996 State Park Rd?

A new gas-insulated switch station building for South Padre Substation No. 1057 is planned at the address. The TDLR registration describes it as an 11,110-square-foot building.

Who is building the South Padre Substation No. 1057 building?

The project record names AEP Texas Central Company. It was registered with TDLR on September 10, 2025.

What will the new substation building contain?

The TDLR description says it will house gas-insulated switchgear, transformers, batteries and associated controls.

How large is the new building at South Padre Substation No. 1057?

The registered project is for an 11,110-square-foot building.

How much will the South Padre substation project cost?

The applicant's TDLR estimate for the project is $12.18 million. This is an estimate, not a reported final cost.

What will the substation building be made of?

The project description says the building will be constructed of precast concrete panels.

When was the South Padre Substation No. 1057 project registered?

The TDLR project registration was filed on September 10, 2025. Its project number is TABS2026000572.