Temple police west substation renovation

The City of Temple registered an interior demolition and renovation of its existing fire and police station for law enforcement use on September 30, 2025. The project covers 1,750 square feet, and the applicant estimated its cost at $250,000. Its TDLR record lists the inspection as complete.

Summarized from Texas Department of Licensing and Regulation records · updated Sep 30, 2025

Projects
1
1 filings
Latest filing
Sep 30, 2025
since Sep 30, 2025
Largest scope
1,750 sf
Estimated cost
$250K
state registration

Where this project stands

Inspected · closing out

City of Temple P.D. West Substation

1,750 sq ft · $250K est.

  1. RegisteredSep 30, 2025
  2. Plan review
  3. ConstructionOct '25 – May '26
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Interior demolition and renovation of an existing fire + police station to be used for law enforcement. — city of temple p.d. west substation

    TDLR project registrationRenovation/AlterationInspection Complete1,750 sq ft$250K est.
    Tenant / owner
    City Of Temple P.d. West Substation
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 8420 West Adams Avenue

What is being built at 8420 West Adams Avenue in Temple?

The City of Temple registered an interior demolition and renovation of the existing fire and police station for use as the City of Temple P.D. West Substation. The TDLR project record is dated September 30, 2025.

Is a new police station coming to 8420 West Adams Avenue?

The record describes renovation of an existing fire and police station for law enforcement use, not construction of a new building. The TDLR registration lists the project as an alteration.

When was the West Adams police substation renovation registered?

The TDLR project registration was filed September 30, 2025. Its project number is TABS2026002124.

How much will the City of Temple substation renovation cost?

The applicant's estimated cost for the project is $250,000. The TDLR record lists 1,750 square feet.

What's being renovated near Extraco Banks on West Adams?

At 8420 West Adams Avenue, the City of Temple registered interior demolition and renovation of an existing fire and police station for law enforcement use. The project is near Extraco Banks at 8205 West Adams Avenue.

Is the West Adams police substation project complete?

The TDLR record lists the project status as “Inspection Complete.” It does not state when the renovated substation will begin operating.