groundranger
Active · latest filing Oct 2026Commercial

13572 N. Main Street

Westlake, TX 76262 · Dal130 - Data Center, Dal130 - Auxiliary Water Building + 1 more

DAL130 data center campus registered in Westlake

TDLR registrations dated October 2, 2026, describe new construction at this multi-tenant commercial site: a roughly 224,152-square-foot data center, a 5,000-square-foot auxiliary water building and a 1,500-square-foot access control building. The data center registration lists an estimated cost of $83 million; the registrations list separate estimates for the two supporting buildings.

Summarized from Texas Department of Licensing and Regulation records · updated Oct 2, 2026

Projects
3
3 filings
Latest filing
Oct 2, 2026
since Oct 2, 2026
Largest scope
224,152 sf
Estimated cost
$83M
state registration

Where this project stands

In state plan review

DAL130 - Data Center

224,152 sq ft · $83M est.

  1. RegisteredOct 2, 2026
  2. Plan reviewnow
  3. ConstructionDec '26 – Jun '27
  4. Inspected
  5. Closed

Construction is scheduled to start Dec 1, 2026. Subcontractors and suppliers are usually picked in the weeks before.

4 contacts on this project · 3 phone numbers

Permit & project history

3 projects
  1. DAL130 - Data Center

    New construction of a data center - 224,152 square feet +/- — circle t ranch dal130 campus

    TDLR project registrationNew ConstructionProject Registered224,152 sq ft$83M est.
    Tenant / owner
    Dal130 - Data Center
    Design firm
    Pro
    Contact
    Pro
  2. New construction of a auxiliary water building - 5,000 square feet +/- — circle t ranch dal130 campus

    TDLR project registrationNew ConstructionProject Registered5,000 sq ft$45M est.
    Tenant / owner
    Dal130 - Auxiliary Water Building
    Design firm
    Pro
    Contact
    Pro
  3. New construction of an access control building - 1,500 square feet +/- — circle t ranch dal130 campus

    TDLR project registrationNew ConstructionProject Registered1,500 sq ft$15M est.
    Tenant / owner
    Dal130 - Access Control Building
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 13572 N. Main Street

What is being built at 13572 N. Main Street in Westlake?

TDLR registrations describe a data center and two supporting buildings: an auxiliary water building and an access control building. The records were filed October 2, 2026.

Is a data center planned for 13572 N. Main Street?

Yes. TDLR registration TABS2027002672 describes new construction of a roughly 224,152-square-foot data center as part of the DAL130 campus.

What buildings are included in the DAL130 campus project?

The registrations list a data center, a 5,000-square-foot auxiliary water building and a 1,500-square-foot access control building. All three were registered on October 2, 2026.

How large is the DAL130 data center?

The TDLR registration lists the data center at approximately 224,152 square feet. It also lists separate supporting buildings of 5,000 and 1,500 square feet.

How much is the DAL130 data center estimated to cost?

The TDLR registration for the data center lists an estimated cost of $83 million. This is the applicant's estimate for that registration, not a reported total project cost.

When was the DAL130 project registered?

The three TDLR project registrations are dated October 2, 2026. They cover the data center, auxiliary water building and access control building.

Email me when plan review is complete